BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/S
xxxxxx …
APPELLANT
VERSUS
M/S
xxxxxx … RESPONDENT
INDEX
|
S.NO |
PARTICULAR NAME |
PAGE NO. |
|
1 |
MEMO OF PARTIES |
|
|
2 |
APPEAL UNDER THE PROVISION OF SECTION 19
MICRO, SMALL AND MEDIUM ENTERPRISES DEVELOPMENT ACT, 2006 (MSMED, ACT 2006)
READ WITH THE PROVISION OF SECTION 34 SUB CLAUSE 2 OF THE ARBITRATION AND
CONCILIATION ACT, 1996 READ WITH SECTION 151 OF CODE OF CIVIL PROCEDURE 1908
AS PREFERRED BY THE APPELLANT AGAINST THE ORDER AS PASSED BY THE LD SOLE
ARBITRATOR WHILE ADJUDICATING THE ARBITRAL PROCEEDINGS AS PREFERRED UNDER THE
PROVISION OF MICRO, SMALL AND MEDIUM ENTERPRISES DEVELOPMENT ACT, 2006
(MSMED, ACT 2006) VIDE ORDER DATED THE XXXXX ALONG WITH SUOPPORTING AFFIDAVIT |
|
|
3 |
STATEMEMT OF TRUTH |
|
|
4 |
ANNEXURE A-1 COPY OF ORDER DATED xxxxxx |
|
|
5 |
ANNEXURE A-2 Authority Letter |
|
|
6 |
ANNEXURE A-3 SCREENSHOT OF THE COMPANY AFFIRM QUA THE
RESPONDENT DETAILS |
|
|
7 |
ANNEXURE A-4 COPY OF STATEMENT OF CLAIM |
|
|
8 |
ANNEXURE A-5 COPY OF STATEMENT
OF DEFENCE ALONGSIDE DOCUMENTS COUPLED WITH THE COUNTER CLAIM AS RAISED BY
RESPONDENT |
|
|
9 |
ANNEXURE A-6 (COLLY) COPY OF DOCUMENTS AND
REJOINDER |
|
|
10 |
ANNEXURE A-7 COPY OF AFFIDAVIT AND
ADMISSION AND DENIAL OF DOCUMENTS,REJOINDER TO COUNTER CLAIM ANE EVIDENCE |
|
|
11 |
ANNEXURE A-8(Colly) COPY OF EVIDENCE BY WAY OF AFFIDAVIT |
|
|
12 |
ANNEXURE A-9 (colly) COPIES OF
APPLICATIONS, REPLIES AND DOCUMENTS AS
WELL AS THE ORDER |
|
|
13 |
INTERIM
APPLICATION FOR ON BEHALF OF THE APPLICANT/APPELLANT UNDER THE PROVISION OF
SECTION 5 READ WITH SECTION 14 OF THE LIMITATION ACT TO CONDONE THE 183 DAYS
OF DELAY IN FILING OF THE PRESENT APPEAL BEFORE THIS HON’BLE COURT ALONG WITH
AFFIDAVIT |
|
|
14 |
COURT FEES |
|
|
15 |
VAKALATNAMA |
|
APPELLANT
Through
Xxxxxx
ADVOCATES FOR
Xxxxxx
Xxxxxx
Xxxxxx
XXX
New
Delhi
XXXXXX
BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/S
xxxxxx … APPELLANT
VERSUS
M/S
xxxxxx
…
RESPONDENT
M/s
xxxxxx
Through
its Partner namely Mr. xxxxxx
Having
their Address at
Xxxxxx
New
Delhi …
APPELLANT
VERSUS
M/s
xxxxxx
Through
its director namely Mr. xxxxxx
Having
their Registered Office at
xxxxxx
New
Delhi
…
RESPONDENT
APPELLANT
Through
Xxxxxx
ADVOCATES FOR
Xxxxxx
xxxxxx
NEW DELHI-110008
New
Delhi
xxxxxx
BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/s
xxxxxx
Through
its Partner namely Mr. xxxxxx
Having
their Address at
Xxxxxx
New
Delhi …
APPELLANT
VERSUS
M/s
Xxxxxx
Through
its director namely Mr. xxxxxx
Having
their Registered Office at
Xxxxxx
New
Delhi …
RESPONDENT
APPEAL UNDER THE PROVISION OF SECTION 19 MICRO, SMALL
AND MEDIUM ENTERPRISES DEVELOPMENT ACT, 2006 (MSMED, ACT 2006) READ WITH THE
PROVISION OF SECTION 34 SUB CLAUSE 2 OF THE ARBITRATION AND CONCILIATION ACT,
1996 READ WITH SECTION 151 OF CODE OF CIVIL PROCEDURE 1908 AS PREFERRED BY THE
APPELLANT AGAINST THE ORDER AS PASSED BY THE LD SOLE ARBITRATOR WHILE
ADJUDICATING THE ARBITRAL PROCEEDINGS AS PREFERRED UNDER THE PROVISION OF
MICRO, SMALL AND MEDIUM ENTERPRISES DEVELOPMENT ACT, 2006 (MSMED, ACT 2006) VIDE
ORDER DATED THE 1ST OF DECEMBER 2023
MOST RESPECTFULLY SHOWETH
A. PURPOSE OF THE PRESENT APPEAL
1.
The Appellant before
this Hon’ble Court is preferring the present appeal under the provision of
Section 19 of MSMED Act, 2006 read with the Section 34(2) of the Arbitration
and Conciliation Act, 1996, for short “Arbitration Act” and with Section
151 of the Code of Civil Procedure Code, 1908, for short “Civil Code”,
whereby, the Appellant is challenging the Order dated xxxxxx , for short “Impugned
Order” on a limited aspect, of the fact that the Respondent was directed to pay
a sum of INR xxxxxx/- Inclusive of Interest alongside the Litigation Cost
against a claim of INR xxxxxx /- inclusive of interestas filed by the
Appellant before the Learned Arbitrator in the Statement of Claim. The Copy of the Impugned Judgment dated xxxxxx
2.
is
annexed and appended as Annexure A-1 alongside the present petition.
B.
BRIEF
INTRODUCTION
3.
That the Appellant is
a Firm registered under the provision of Indian Partnership Act and the
Appellant Firm, is an emerging firm which deals in the Manufacture of Bearings,
Machines, Driving Elements and the Claimant Company is also in the Production
and Manufacturing of ALU Castings for LED Street Lights, Fixtures Etc and at
Present the Claimant Company is operating from the Address as mentioned in the
Memo of Parties and the Present Claim Petition under the Provision of Micro,
Small, Medium Enterprises Act is filed by Sh. xxxxxx, who’s Authority Letter is appended along-side
the Present Claim Petition as Annexure A-2 alongside the present petition.
4.
That the Respondent
No.1 is a Company as registered within and under an ambit of the Companies Act,
1956 as amended from time to time and at Present the Defendant No.1 Company is
operating from the Address at mentioned in the memo of Parties, which is xxxxxx
New Delhi. That the Defendant Company is having its Corporate Identification
Number as xxxxxx and also at xxxxxx RIICO Industrial Area, xxxxxx Rajasthan is
the office where the Books of Account and Papers are maintained by Respondent,
through its director namely Sh. xxxxxx bearing DIN No. xxxxxx Sh. xxxxxx
bearing DIN No. xxxxxx and Smt. Xxxxxx bearing DIN No. xxxxxx
, who are managing the affairs of the Respondent Company. That the Screenshot from the Company of
Affair qua the Respondent’s Detail is also appended as Annexure A-3 alongside
the present petition.
C. BACKGROUND OF THE PRESENT CASE
5. That the Defendant firm through its directors in and
around the beginning of 2017 approached the Appellant’s Firm and represented themselves
as Directors of the Respondent Company, who were also managing the Daily Day to
Day Affairs and management of the Respondent Company. Sh. Xxxxxx Sh. Rachit and
Smt. Xxxxxx represented to be carrying out all the management responsibilities
of the Respondent Company coupled with the fact that the said mentioned
directors are also entrusted with Substantial Powers of Management.
6. The afore-mentioned directors of Respondent Company gave
personal guarantees to the Appellant Firm coupled with assuring the Appellant
Firm that the Respondent Company through mentioned directors shall make the
payment immediately post the receipt of Goods/Material from the Appellant Firm.
7. That starting from the year 2017, the Respondent
through the mentioned directors started to place numerous orders to the Appellant
Firm and it was mutually agreed between the parties and also as per the
Tax/Retail Invoices that the payment of the due amount, being due against the
goods being supplied by the Appellant’s Firm to the Respondent Company, shall
be paid/remitted by the directors of Respondent No.1 within the stipulated
period of days as prescribed under the Law.
8. That starting from the year 2017, the Respondent
through its Directors personally visited the Office of the Appellants Firm and
subsequently placed numerous orders. Consequent to which, all such Order/Orders
of the Respondent No.1 wasduly fulfilled by the Appellants Firm. That the
Appellants firm, as and when requested by the Respondent Company through its
director, supplied goods to the Respondents in the same manner and as per the
specifications as were requested by the Respondent Company through its director.
9. That against the orders being placed by the
Respondent Company to the Appellants Firm at their Delhi office, goods were
supplied by the Appellant and such goods were accepted by the Respondent
without any protest or demur of any manner whatsoever.
10. That it is pertinent to mention that as and when an
order was placed by the Respondent, the Appellants Firm subsequently delivered
such goods, being of topmost quality and being as the per the specifications
ordered by the Respondent, and the goods were supplied by the Appellants Firm
to the Respondent by or before the time period as requested by the Respondent.
11. Apropos, to afore-mentioned the invoice(s) being
issued by the Appellant Firm to the Respondent, and the Respondent accordingly
made payments to the Appellant at their Delhi office on a running account
basis.
12. That the Respondent Company through its directors,
in light of the mutually accepted terms and conditions between the parties
placed their order, and subsequently, against such order placed by the
Respondent, the Appellant Firm company supplied the Goods to the Respondent in
accordance to the specifications and satisfaction of the Respondent. It is
pertinent to mention herein that the Respondent without any protest or demur
accepted the Goods being supplied by the Appellant Firm.
13. That it is pertinent to mention that the Goods were
supplied by the Appellant Firm through the medium of a transport carrier, to
which the Appellant Firm had delivered the Goods to the Respondent against the
invoices being issued by the Appellant Firm to Respondent and the Payments were
made on the Running Account basis and the Respondent made payments to the Appellant
at their Delhi office on a running account basis. The invoices are also annexed
alongside the present petition.
14. That the Appellant Firm very fairly states before
this Hon’ble Court that on the xxxxxx of January xxxxxx, the Respondent also
admitted and confirmed the Accounts and the Balance Payment i.e., the Principal
Amount was outstanding to an extent of INR xxxxxx /- which was to be paid by
the Respondent to the Appellant Firm. That on xxxxxx of January xxxxxx, the Appellant
Firm by invoking the Provision of Insolvency Act, issued a Demand Notice
demanding payment of an unpaid debt to an extent of INR xxxxxx/- in which INR xxxxxxwas
pending towards the Principal Amount and INR xxxxxx/- was pending towards
Interest and the said Demand Notice very specifically stated that the payments
are to be made in accordance with the Provisions of MSME Act as the Appellant
Firm is registered under the Provision of MSME Act and the Respondents were at
continuous default of the said outstanding amount which can also be confirmed
by their own admission of admitting the Liability of the Amount.
15.
That the Appellant
Firm Fairly states before this Hon’ble Tribunal that post the receipt of the
Demand Notice, the Respondents through its director approached the Partner of
the Appellant Firm and Respondent requested to settle the disputes as directors
of Respondent Company assured that the Principal Amount as stated in the Demand
Notice shall be paid by the Respondent to the Appellant Firm and subsequent to
which, a Settlement Agreement was made and it was explicitly made clear that
the Outstanding Amount shall be paid in Four Instalments vide Cheque No. xxxxxx
and the Respondent through its directors confirmed that in the event of breach
of payment plan/schedule, the Respondents through its director shall be liable
to pay the entire amount with an interest as claimed in the Demand Notice of xxxxxx.
16. The Appellant Firm states fairly before this Hon’ble
Tribunal that two instalments vide Cheque No. xxxxxx was paid as the same can
also be verified from the Statement of Account of the by the Appellant Firm as
well as the Respondent. Subsequent to the clearance of the Afore-mentioned
Cheques, the director of Respondent Company once again requested the resumption
of business amongst the Parties and again on the personal assurances and
representations as warranted by the Respondent, the Appellant Firm once again
started the Business Trade inter se between the Parties and on request, the
Cheque No. xxxxxx and xxxxxx were returned back as it was assured by the
Respondent that said payment shall be made during the course of the running
account as the financial status of Respondent Company was not that great and
only once the business of Respondent is restored back to its original then only
the payments shall be released over.
17. Owing to the Cordial Business Relationship, inter
se, between the Parties, the Appellant Firm started once again to supply the
goods as per the specifications as rendered down upon by the Respondent and
being satisfied with the quality of the Goods, the Respondent once again
started making Payments qua the Running Account basis. That the Payments
starting from the xxxxxx th of September xxxxxx till the last invoice dated the
xxxxxx of October xxxxxx , the Respondent failed to make the payment of the
Amount to the Claimant Firm as required under the Provision of Section 15 of
the MSMED Act.
18. As on xxxxxx
of June 2022, the Total Principal Amount as rendered outstanding between the
Parties to the Proceedings were to an extent of INR xxxxxx and also the
Interest on Delayed Payments as to be levied under the provision of MSMED Act.
19. The Appellant had no other option but to file a
Claim under the Provision of Section xxxxxx of the MSMED Act before the Facilitation
Council as the Respondent failed to make the Payment under the Provision of
Section 15 of the MSME Act and on failure to Pay the Interest under the Purview
of Section 15 and 16, the Application under the Provision of Section 18(1) was
filed before the Office of the Sub-Divisional Magistrate and the same was
registered vide File No.
xxxxxx. Notice was issued to the Respondent, who,
appeared and preferred a reply before the Office of the Sub-Divisional
Magistrate and the objections were taken primarily on pretext of Interest Rate
coupled with Settlement, to which in reality was not even complied by the
Respondent and all the other contents were not denied, hence the same becomes
an admission on part of the Respondent that the Goods were delivered and that
too without any protest and also the Principal Amount was admitted and the only
objection was taken with regard to the Calculation of the Interest Amount.
S
20. Despite the Indulgence of the Learned Council under
the Provision of 18(2) of the Act In order to conduct a conciliation in the
matter or by providing an alternate dispute resolution service for conducting
conciliation. Despite the best of possible assistance as rendered down up by
the Learned Council and the Appellant, the Respondent miserably failed to
respect the Proceeding and on failure on part of the Respondent despite the
fact that the services stood rendered by the Appellant and the Respondent was
not discharging the payments, the Council deemed it appropriate to refer the
Matter to before the Present Arbitration Centre.
21. That all the director of the Respondent Company, as
stated afore-said are jointly and severally liable to the Claimant Firm and
because of the Personal Guarantees and Assurances as rendered down upon by the
Respondent coupled with Fraud been played by the Respondent, the Corporate Veil
is required to be lifted in the Present Matter and to clear the Legitimate dues
of the Appellant Company under the Provision of Section 15 and 16 of the MSME
Act which requires the Respondent to make the payment to the Appellant Company within
specific days of the submission of the Invoice and the Section 15 of the Act
uses the word “Shall” hence making it mandatory for the Respondent to clear the
dues within the specific period of days of submission of the Appellant Invoice
and in any case, it is statutorily incumbent in law that a buyer cannot exceed
the period of 45 Days from the date of Acceptance of service for discharging
the Payments.
22. The Compound Interest is mandated by MSMED Law and
the provision also uses the word Shall, and is therefore mandatory in
nature and the law has mandated that the Compound Interest has to be paid by
the Buyer at Three Times of the Bank Rate as notified by the Reserve Bank of
India, making the said provision applicable on all the pending dues and belated
payments that stand due on the Respondent and in the issue at hand, the
calculation of compound interest clock commences from the xxxxxx to xxxxxx of
receipt of Claimants invoice by the Respondent which remained uncleared by the
Respondent within the given time frame.
23. Consequent to the above, the Respondent is duty
bound and obligated in law to clear and principal amount and interest of the Appellant
as enshrined in Section 17 of the Act and the Respondent has miserably failed
to comply with the provisions of Law and deliberately violated the same despite
several reminders and no action was taken by the Respondent on payment of the
dues towards the Appellant.
24. That, as such, it is clear from the above-mentioned
facts, that the Respondent has failed to make payments as per the
aforementioned section of the MSMED Act and as such the Appellant, approached
the Ld. Tribunal, as enshrined under the relevant provision of Law.
25. The Appellant, submitted the claim, before the
Learned Tribunal by virtue of the statement of claim as per the provision of
MSMED Act on xxxxxx alongside the documents, which is filed and annexed as
Annexure A-4 Colly.
26. The Respondent then on xxxxxx filed its Statement of
Defence, inter alia, praying for dismissal of the Statement of Claim and
at the same time the Respondent also filed a Counter Claim inter se raising
a claim of INR xxxxxx/- on account of Damage on account of loss of sale and INR
xxxxxx /- as claim for damages on account of Loss of reputation and mental
distress plus costs and interest. The Copy of Statement of Defence alongside
documents coupled with the Counter Claim as raised by Respondent is annexed and
appended alongside the present petition as Annexure A-5 Colly.
27. The Petitioner then on xxxxxx , filed the Rejoinder
to the Statement of Defence as filed by the Respondent to the Claim Petition
alongside the Statement of Defence to the Counter Claim as filed by Respondent.
In addition to the same, the Petitioner then filed an affidavit of admission and
denial and Evidence by way of an Affidavit before the Ld. Tribunal over an
e-mail. The Copy of Documents as filed is annexed and appended alongside as
Annexure A-6 Colly. The Respondent on xxxxxx had filed the affidavit of
admission and denial of documents and the same is annexed and appended as
Annexure A-7.
28. In addition to above, the Petitioner on xxxxxx filed
the Evidence by way of an affidavit and the Respondent on xxxxxx filed the
Evidence by way of an affidavit dated xxxxxx and the same is exhibited as
Annexure 8 Colly, whereas in the Counter Case, the Evidence was filed by
Counter Claimant on xxxxxx 2023 and the Petitioner on Evidence in the Counter
Claim case and the same is annexed and appended. It is stated that the
directors of the Respondent Company were pleaded over in the said arbitration,
however, an interim application seeking deletion of directors were filed, which
was thus subsequently dismissed. In addition to the same, the Appellant also
filed that interim application seeking permission to cross examine the AR of
the Respondent, and the same was also dismissed by the Ld. Arbitrator for the
reasons best known to the learned arbitrator. The Copies of the Documents as
well as the order is annexed and appended as Annexure A-9 Colly.
D. ISSUES AS FRAMED BY THE
LEARNED TRIBUNAL
29. The Learned Arbitrator post the perusal of the
pleadings of the case inclusive of Arbitration as well as Counter Claim framed
the following Questions to adjudicate the present matter which is evident as
per Para 9A of the Impugned Judgment which are as follows-
i.
Whether the
parties come under the purview of MSMED Act, 2006 or not? Whether the Claimant
is not entitled to get any relief through this MSME Arbitral Tribunal, being
registered with MSEFC Subsequent of date of entering into contract as well as
subsequent of rendering its said services to respondent, as contended by Ld.
Counsel for respondent.
ii.
Whether claimant
is not entitled to seek remedy from this platformi.e. MSME Arbitral Tribunal,
being an unregistered partnership firm as barred under section 69 Partnership
Act, 1932?
iii.
Whether the bills/invoices raised by claimant to
respondent andbasing upon instant claim is raised, are bogus and not genuine?
iv.
Whether the
claim raised herein by claimant, is time barred, ascontended by respondent?
v.
Whether under
effect of Novation of Contract, as provided undersection 62 Indian Contract
Act, 1872, being resumption of businesswith it by claimant after having
terminated of settlement-agreement,respondent was not to perform the original
(said settlement-agreement)agreement?
vi.
Whether Clause
Force Majeure applies to the present matter or not?
vii.
Whether defence
of respondent that goods received to it from claimant were of inferior quality
/ low grade is plausible and sustainable in view of documentary evidences
available on record?
viii.
Whether,
respondent is liable to pay entire claim amount with interest of INR xxxxxx /-,
if not, then how much?
E.
FINDINGS
BY THE LD. ARBITRATOR
30.
Pursuant to the
question as framed under the arbitral proceedings, the Ld. Arbitrator dealt
with the questions perusal of the agreements and on the basis of documents on
record. With Respect to Serial no (i) the Ld. Arbitrator held as under
As argued by the
learned counsel for the claimant, the claimant is a legitimate enterprise as it
is a Company· registered with the Ministry of MSME, India, under its Udyog
Aadhaar No.DLxxxxxx dated May xxxxxx (subsequently replaced by Udyam Registration
No. xxxxxx. The company, structured as a partnership firm, specializes in the
manufacturing and supply of bearings, machines, driving elements, and aluminium
castings for LED street lights and fixtures, operating from its base in xxxxxx Industrial
Area, Delhi.
Given this
information, it is clear that the claimant is a valid supplier under the MSMED
Act, 2.006, even during the ongoing business relationship with the respondent.
This business relationship commenced in 2017 and continued until October xxxxxx
, the date of the last invoice. raised. While the learned counsel for the
respondent has challenged the maintainability of the instant claim petition
under the provisions of the MSMEP Act, 2006, arguing non-compliance with
Section 8 of the MSMED Act, 2006, due to
the absence of a required memorandum filed by the claimant, this contention is
misplaced. The claimant is not obligated to file such a memorandum as mandated
in Section 8 of the MSMED Act, 2006, since it is optional for Micro & Small
Enterprises to file it.
Also, this issue
has been set at rest as Hon 'ble High Court of Delhi in its latest judgement
titled as "xxxxxx Vs. xxxxxx by
Justice xxxxxx " which held that even if during the course of supply, if
supplier gets itself registered with the MSEFCthen also that supplier will be
entitled to seek its due claim under the provisions of MSMED Act 2006.
The aforesaid
legal proposition is further upheld by the Hon'ble bench of Delhi High Court in
LPA No xxxxxx titled as "xxxxxx decided
by . xxxxxx
In light of all
the above considerations, it is evident that the respondent's argument
challenging the claimant's recourse to the MSMED Act, 2006 is untenable.
Despite the claimant's admission that their registration occurred on May xxxxxx
it is an undisputed fact that the business relationship with the respondent,
commencing in 2017, continued until October xxxxxx well after the claimant's
registration with the MSEFC under the MSMED Act, 2006.
Furthermore, the
learned counsel for the respondent contends that since the claimant, being a
partnership firm, is not a .registered firm, it does not qualify as a valid
supplier under Section 2(n)(iii) of the MSMED Act, 2006.
However, this
contention of the respondent is not sustainable. As observed, Section 2(n)(iii)
of the MSMED Act, 2006 stipulates -that a supplier can be any company,
cooperative society, trust, or a body that is registered or constituted under
any law currently in force, and is engaged in the production of goods by micro
or small enterprises and in rendering services. In this case, the claimant,
though not a registered partnership firm, is constituted under the provisions
of The Partnership Act, 1932, and its registration for conducting business is
not mandatorily required. Moreover, this tribunal concurs with the claimant's
counsel that Section 2(n)(iii) of the MSMED Act, 2006, in addition to the terms
"company, cooperative society, and trust," also includes the phrase
"or a Body," which encompasses the Claimant. Thus, the
claimantsatisfies the definition and requirements of Section 2(n)(iii) of the
MSMED Act, 2006.
Therefore,
this tribunal, in its considered observation and opinion, determines that the
claimant is indeed entitled to avail the benefits of the .MSMED Act, 2006 for
its claim before this arbitral tribunal. Consequently, the present question is
resolved in favor of the claimant and against the respondent.
31.
With Regard to Issue
No.(ii) i.e. No Entitlement of claimant to seek remedy from this MSME Arbitral
Tribunal being not registered partnership firm, as required under section 69
The Partnership Act, 1932, the Learned Arbitrator held as under
The learned
counsel for the respondent has raised an objection based on Section 69 of The
Partnership Act, 1932, arguing that claimant is not a registered partnership firm,
it cannot seek any remedy under its firm name. As the claim herein is filed in
the name of the firm, the counsel contends that it should be dismissed or
rejected.
In contrast, the
counsel for the claimant submits that while the registration certificate could
not initially be placed on record, the claimant is indeed a registered
partnership firm since 2004 as evidenced by the registration certificate issued
under No. xxxxxx dated
June xxxxxx by the office of the commissioner of industries, xxxxxx.
The Claimant has subsequently produced this certificate.
The learned
counsel for the respondent has strongly objected to the inclusion of this
registration certificate in the records, arguing that the matter is not at the
stage of final arguments and that at this late stage, no new document should be
accepted. This tribunal concurs with the submission of the learned counsel for
the respondent in this regard. However, it is observed that even if the said
registration certificate of the claimant is not admitted into the record, the
claimant is still entitled to seek a remedy from this platform. The reason
being the present proceedings are arbitration proceedings and cannot be equated
to or treated as a lawsuit.
Further, as this
Arbitral Tribunal in no case is a "Court" ,as per definition of
Section 2 of Arb. & Cone. Act, 1996, so also it is quite clear that Section
69 of The Partnership Act, 1932 doesn't apply to any proceeding before this
tribunal. Reliance may derived from judgment titled as "xxxxxx
It is
thus, this question is answered in negative against the respondent and in
favour of claimant by holding that claimant well entitled to seek claimed
remedy before this platform, this arbitral tribunal.
32.
With Regard to Issue
No.(iii) i.e. bills/invoices raised by claimant to respondent. are bogus and
not genuine, to which the Ld. Arbitrator post the perusal of the documents
coupled with arguments as addressed gave the finding as below
This tribunal
finds the submission of the respondent to be wholly misconceived and untenable.
The reasoning for this conclusion lies in the fact that the respondent, having
acknowledged its liability, entered into and executed a settlement agreement on
January xxxxxx., Subsequently, it is inconsistent and contradictory for the
respondent to challenge the bills, especially after entering into a settlement.
Moreover, all invoices in question are GST-paid invoices, and there is no
indication from the respondent that it has not taken or availed of the GST
inputs from these bills/invoices. Furthermore, the respondent’s own ledger
indicates and outstanding balance of INR xxxxxx /-. Consequently, the
respondent’s characterization of the claimants bills as bogus is an incorrect
submission. Therefore,
this question is resolved in the negative against the respondent and in favour
of the claimant, affirming that the bills/invoices are not bogus and false.
33. With Regard to Issue No.(iv) i.e. Claim is time
barred or not, to which the Ld. Arbitrator post the perusal of the documents
coupled with arguments as addressed gave the finding as below
The respondent
contends that the claim raised by the claimant is time-barred because the
business relations commenced on October 16, 2017 (the date of the first
invoice), and the claim petition was filed before this tribunalon August xxxxxx
. They argue that even considering the execution of the settlement agreement on
January xxxxxx , the claim petition is still time-barred as it wasfiled well
beyond the permissible three-year period, which would have expired in January
2023.
Countering this,
the learned counsel for the claimant submits that the claim petition is within
the limitation period and,therefore, is not barred by time. He argues that
since there was an unchallenged running account of the respondent being
maintained by the claimant, and there were demands based on that account,Article
1 of the Schedule of the Limitation Act, 1963 applies. According to Article 1,
the last cause of action arises at the close of the year when the last entry of
the transaction is made in that account. In this case, the ledger of the
respondent {Exb.CW-1/ 1) pages 122 to 127 of SOC shows the last transaction
made via Voucher no xxxxxx on xxxxxx .
Therefore, the claim petition filed on August xxxxxx , falls well within the
three-year limitation period ending on June xxxxxx.
Consequently,
this question is answered in the negative against the respondent and in favour
of the claimant, confirming that the claim petition is not time-barred.
34. With Regard to Issue No.(v) i.e. Respondent's No
Liability to honour Settlement- Agreement under effect of Novation of Contract
being resumption of business by claimant with it as per section 62 Contract
Act, 1872, to which the Ld. Arbitrator post the perusal of the documents
coupled with arguments as addressed gave the finding as below-
The learned
counsel for the respondent argues that the resumption. of business relations
with the claimant after the nonÂcompliance of the settlement agreement dated
January xxxxxx, constitutes a novation of the contract. They contend that, by
virtue of Section 62· of the Indian Contract Act, .1872, the .respondent is not
obligated to perform or honor the said settlement agreement, thereby absolving
them of any liability towards the claimant.
In response, the
learned counsel for the claimant counters this submission by referring to
Clauses 6 and 7 .3 of the said settlement agreement dated January xxxxxx. They
point out that Clause 6 permits any modification of the agreement only through
a written document signed by both parties. Since there is no suchdocument that
is written and signed by both parties, they argue, there has been no novation
of the settlement agreement. Furthermore, Clause 7 .3 of the settlement
agreement stipulates that it is an irrevocable agreement and cannot be
dissolved under any circumstances.
Thus, based on
the provisions of the settlement agreement and the absence of a written and
mutually signed document indicating any modification or novation, the
claimant's counsel asserts that the original terms of the settlement agreement
remain binding and enforceable.
However, it is
an acknowledged fact between the parties that despite the non-compliance with
the settlement agreement, given that the respondent failed to pay the last two instalments of Rs. xxxxxx each
within the scheduled timeframe specified in the agreement and has only made a part-payment
to the claimant during an extended period of approximate 5 months. It isalso a
recognized fact that the claimant has accepted this part-payment from the
respondent without objection Furthermore, the parties resumed their
transactions, with the claimant making the last sale on October xxxxxx, and the
respondent completing the last payment to the claimant via bank transfer on June
xxxxxx
In light of the
aforementioned circumstances, this tribunal holds the considered view that the
settlement agreement between the parties has been duly complied with and
concluded after the claimant received the ·1ast • payment on Xxxxxx. Therefore,
the claimant is not entitled to reopen the issue of delayed payments for
transactions that occurred before Xxxxxx. Subsequent transactions, which
resumed from Xxxxxx, are not part of the settlement agreement between the
parties and are conducted under a mutual understanding without any formal
agreement.
Thus,
this question is resolved in favor of the respondent, specifically regarding
the finding that the respondent has fulfilled the obligations of the settlement
amount as per the settlement agreement and is not liable to pay the claimant
for any transactions that occurred before Xxxxxx.
35. With Regard to Issue No.(vi) i.e. Filing of claim
petition by authorized person o.r not, to which the Ld. Arbitrator post the
perusal of the documents coupled with arguments as addressed gave the finding
as below-
In response, the
learned counsel for the claimant referred to Paragraph 1 of the claim petition
and argued that the claimpetition was file Mr. xxxxxx , who is one of the
partners of the claimant firm, and therefore, it was filed properly by an
authorised person.
There is no
doubt that Mr. Xxxxxxis a properand authorized individual to file the claim on
behalf of the claimant firm.
Consequently,
the present question is resolved against the respondent and in favor of the
claimant, affirming that the claim petition was properly filed by an authorized
person.
36. With Regard to Issue No.(vii) i.e. Applicability of
Force-Majeure into the present matter, to which the Ld. Arbitrator post the
perusal of the documents coupled with arguments as addressed gave the finding
as below-
This tribunal, in its findings on the related issues
in 9.B.v observes that the settlement agreement between the parties was
effectively concluded after the respondent made the last part-payment on Xxxxxx.
Additionally, the business transactions that resumed from Xxxxxx continued
until Xxxxxxwith the claimant receiving the last payment on June xxxxxx,
without any protest or objection. Therefore,
there was no basis to invoke a plea of force majeure in the current
proceedings, and any such claim is deemed to be without merit.
37. With Regard to Issue No.(viii) i.e. Plausibility of
respondent’s defence of receiving low-graded/inferior quality goods from
claimant, to which the Ld. Arbitrator post the perusal of the documents coupled
with arguments as addressed gave the finding as below-
The tribunal
observes that the respondent's own ledger records an outstanding principal
amount of Rs. xxxxxx/-owed to the claimant, raising questions about the
legitimacy of the alleged rejections of goods worth Rs. xxxxxx /-. Besides a
single email, the respondent has not provided substantial evidence regarding
the quality of the goods supplied by the claimant or any direct loss suffered
due to the alleged inferior quality. Therefore, the tribunal concludes that the
respondent has failed to substantiate its claim that the goods supplied by the
claimant were of inferior quality or low-grade
Consequently,
this question is resolved in the negative against the respondent and in favour
of the claimant.
38. With Regard to Issue qua the Liability of respondent
to pay the entire claim amount of Rs. xxxxxx as principal amount and balance as
interest, to which the Ld. Arbitrator post the perusal of the documents coupled
with arguments as addressed gave the finding as below-
Therefore,
considering the facts of the present case, this tribunal views that the
claimant is only entitled to delayed payment interest as per the provisions of
the MSMED ACT, 2006 from June 14,2022, the date of the last payment received
from the respondent and only on the principal amount of INRxxxxxx. The
Claimant’s request for interest amounting to INR xxxxxx, as per its calculation
sheet is deemed misconceived and is thus rejected
39. The Learned Arbitrator, now while adjudicating the
Counter claim as filed by Respondent and on the pleadings the Ld. Arbitrator
rightly came to the conclusion that upon consideration of all submissions,
pleas and contentions of respective parties and evidences on record, the
Learned tribunal has found that it is clear that counter-claim based upon claim
of suffering loss of sales / revenue to the tune of INR xxxxxx /- is not
supported with any documentary evidence which may substantiate or even reflect
the actual loss suffered to CC, more particularly only because of claimed reason
of non-receiving back the alleged defective/ low-graded material at the end of Appellant.
Said emails nowhere stand out a case that Respondent had directed or demanded Appellant
to take back the alleged defected materials from it. Also, thereis not on
record that alleged supply of defective goods/material was brought to the
notice of Appellant within time, nor even any debit note is supplied/ issued to
the Appellant and same is also not reflecting into / account-statement of Appellant
maintained by Respondent. Henceforth, the Learned Tribunal in total agreement
of the plea of Appellant that for claiming damages, the breach of contract is a
pre-condition and in this whole issue, thereis not any allegations of Respondent
that contract was breached by Appellant in any manner or any given point of
time.
40. Henceforth. The Learned Tribunal rightly, held
that the whole onus to prove its Counter Claim was lying upon the Respondent
and the Respondent failed to prove the case as alleged by Respondent before the
Learned Arbitrator as the Counter claim grounds were similar to what was raised
in the Statement of Defence and henceforth
the Ld. Tribunal without any doubt pleased to dismiss the Counter Claim of
Respondent.
41. The Learned Arbitrator while awarding the interest
to the amount as held in one of the questions before the Ld. Arbitrator, more
particularly, to the issue which was held against the Appellant, the Ld.
Arbitrator relied upon the provision of MSMED Act, by placing reliance upon
Section 16 and 17 of MSMED Act to award interest at three times of rate of xxxx
per annum which stands out to be at xxxxx and hence the Ld. Tribunal awarded
the interest of INR xxxxxx against the interest as claimed by Appellant before
the Ld. Arbitrator, the fact which is under challenge before the Ld. Arbitrator
as the same finding of the Ld. Arbitrator is patently wrong and to be
interfered with.
42. The
said order under the provision of Arbitration Act as impugned before this
Hon’ble Court is challenged primarily on the below mentioned grounds which are
as follows.
F. GROUNDS
43.
BECAUSE,the Learned Arbitrator
failed to note the Clauses of the Settlement Agreement and more particularly,
Clause No.3.1, inter alia, which states and records that the Respondent
agrees and confirms alongside acknowledged to pay an amount of INR xxxxxx/- to
the Appellant in order to amicably resolve the present matter, in accordance
with the payment schedule and in lieu of which Four Cheques of INR xxxxxx /-
were issued over by Respondent to the Appellant.
44.
BECAUSE, the
Ld. Arbitrator failed to acknowledge the Clause No.3.2 of the Settlement
Agreement, inter alia, which records that the Respondent irrevocably
agreed and confirmed that the Demand Notice dated xxxxxxx shall remain
in effect and continuance until the payment of the entire dues as mentioned in
Clause 3.1.
45.
BECAUSE, the Ld. Arbitrator
failed to appreciate and take a note of the Legal Notice as mentioned
aforenoted i.exxxxxx, wherein the total amount of debt was of INR xxxxx /- out
of which INR xxxxxx/- was the amount outstanding for Principal and INR xxxxxx/-
was for Interest. It is an admitted fact that the said amount of INR xxxxxx/-
was an admitted amount by the Respondent resulting which only the Settlement
Agreement as afore-mentioned was entered upon by the parties to the present
petition. Perusal of the settlement agreement would reveal that the said
settlement agreement was binding upon on the parties to the present
arbitration, their successors in interest, and present and future affiliates,
subsidiaries, assignees or acquirers, including any acquirer of substantially
all of an asset.
46. BECAUSE,
the
Learned Arbitrator failed to note and acknowledged Clause 3.3 of the Settlement
Agreement, which inter alia, and more specifically stated that the
Respondents will pay the sum of INR xxxxxx/- in accordance with the payment
schedule as mentioned in Clause 3.1 above, the Appellant had agreed to amicably
resolve the present matter in an amount of INR xxxxxx /-. The Learned
Arbitrator patently failed to note the furtherance of the clauses of the
settlement agreement which connoted the intent of the parties to the present
petition as the Respondent vehemently agreed that in event of breach of payment
plan/schedule as mentioned in Clause 3.1 of the Settlement Agreement, the
Respondent shallbe liable to pay the entire amount with interest
as claimed in the Demand Notice of 0 xxxxxx for an amount of INR xxxxxx /- after
deducting the amount already paid by the Respondent.
47. BECAUSE,
the
Learned Arbitrator failed to appreciate the statement of defence on record
wherein the Respondent themselves admitted to the Settlement Agreement and the
Amount of the Legal Notice dated 0xxxxxx and also the fact that the Cheques, as
mentioned above were handed over.
48. BECAUSE,
The
Learned Arbitrator in its order gave a very categorically finding qua one of
the issues which is co-related to the second issues, in which the Learned
Arbitrator despite adjudicated the issues in the favour of Appellant, turned
the clock against the Appellant. The Ld. Arbitrator as held the submissions of
the Appellant to be correct to an extent that the claim as filed by the
Appellant was well within time and the Ld. Arbitrator had also post the perusal
of the pleadings on records and post the submissions has rightly held that it
is an admitted and acknowledged fact between the parties that “despite
the non-compliance with the settlement agreement, given that the Respondent
failed to pay the last two instalments of INR xxxxxx /- each within scheduled
timeframe specified in the agreement and has only made a part payment to the
Appellant.
49. BECAUSE,
the
Learned Arbitrator despite having a conclusive finding qua the fact that the
settlement agreement which was entered upon by the parties by their free will
was anyway not complied with by the Respondent and hence the Respondent
violated the Clause 3.3 of the Settlement Agreement inter alia by which
it was now on Respondent to pay the entire amount of the demand notice minus
the amount already paid, the Learned Arbitrator gave a perverse and patently
wrong finding qua the fact that since the parties to the petition resumed their
transaction, with the Appellant making last sale on xxxxx and Respondent
completing the last payment to the Appellant on June xxxxx coupled with the
fact that the Appellant did accept the part-payment from Respondent without
objection and hence such the Appellant is not entitled to re-open the issue of
delayed payments for the transaction that happened before hand.
50. BECAUSE,
the
said afore-mentioned findings by the Ld. Arbitrator is in complete
contradiction to the documents on record and moreover the admissions which are
quite evident from the documents as filed by Respondent to an extent that there
was no question of Appellant accepting or denying the part-payments (if any),
the parties to the contract was very well governed by the Clause of 3.3 of the
Settlement Agreement which specifically made it clear that if the Respondent
failed to pay the entire amount with interest as claimed in the
Demand Notice after deducting the amount already paid by the Respondent.
51. BECAUSE,
the
Appellant without prejudice to the rights and contention of Appellant states
that the total amount as claimed in the demand notice dated xxxxxx was INR xxxxxx/-
and even if we believe the version of the Respondent and also the fact which
has been acknowledged by Ld. Arbitrator that the payments of First Two
Instalments for an amount of INR xxxxxx/- has been paid and Appellant without
prejudicing the right also if state that even if the payment if we take from 1st
of April 2020 till 6th of July 2020 which were of INR xxxxxx-
coupled with INR xxxxx /-, INR xxxxxx-, INR xxxxxx-, INR xxxxx and INR xxxxxx /-,
the total of which shall come at INR xxxxx /-, henceforth leaving a balance of
INR xxxxxx , by which the Ld. Arbitrator also affirmed that the settlement
agreement has not been complied, therefore Clause 3.3 shall be attracted which
the Ld. Arbitrator failed to appreciate and the result of which the Respondent
was under an obligation to pay INR xxxxxx 1/- i.e., { INR xxxxxx- INR xxxxxx/-
minus INR xxxxxx /-} and by adding an amount of INR xxxxx /- coupled with
interest at the rate as prescribed under the provision of MSMED Act.
52. BECAUSE,
the
Learned Arbitrator out of 9 issues has rightly awarded and held seven issues to
be in favour of the Appellant, however the Ld. Arbitrator had patently failed
to acknowledge the remaining two issues in light of the documents as well as
submissions of the Respondent which makes the present judgment to be perverse
and patently wrong, hence making it in conflict with the public policy of India
and in conflict with the most basic notions of morality and justice.
Henceforth, the present Appeal under the relevant provision of Law is limited
to those two findings as rendered by the Ld. Arbitrator as the last issues is
read in conjunction with issue no.5 as the Learned Arbitrator at one place
mentions that there was a default on part of Respondent and at the other side
rules in favour of the respondent by saying that the respondent has fulfilled
the obligations of the settlement agreement.
53. BECAUSE,
The
term “patent illegality” was explained in detail and brought within the scope
of public policy of India for the first time by the Apex Court in xxxxxx .
However with the amendments to Section 34 of the Arbitration & Conciliation
Act, 1996 (hereinafter referred to as the said Act), made by the Arbitration
and Conciliation Amendment Act, 2015, with effect from xxxxx , the expansion of
the term public policy of India as interpreted by Courts previously has been
done away with.
54. BECAUSE,
The
Law Commission examined and submitted its 246th Report on "Amendments to
the Arbitration and Conciliation Act, 1996" in August, 2014 and
recommended various amendments in the said Act. The proposed amendments were
intended to facilitate and encourage Alternative Dispute Mechanism, especially
arbitration, for settlement of disputes in a more user-friendly, cost effective
and expeditious disposal of cases since India is committed to improve its legal
framework to obviate in disposal of cases.The 246th Report of the Law
Commission recommended considerable changes to Section 34 of the said Act. The
246th Law Commission Report proposed amendments to the said Act, narrowing down
the grounds of challenge the Arbitral Award, apart from providing for
appointment of independent, impartial and neutral arbitrators, amongst several
other amendments. The judgment in ONGC’s case stated supra along with the
judgment in ONGC v. Western Geco International Ltd.xxxxxx ) has been expressly
done away with.
55. BECAUSE,
Both
Sections 34 and 48 of the said Act have been brought back to the position of
law contained in xxxxx Ltd. V xxxxx. (1994) Supp (1) SCC 644 : (AIR 1994 SC
860), where "public policy" will now include only two of the three
grounds set out therein, i.e., "fundamental policy of Indian law" and
"justice or morality" in addition to the ground where making of the
award was induced or affected by fraud or corruption or was in violation of
Section 75 or Section 81 as provided in Section 34 of the amended Act . The
ground relating to "the interest of India" stated in the said
Judgment is no longer available as valid ground. "Fundamental policy of
Indian law" is now to be understood as laid down in Renusagar (supra).
Meaning of "Justice or morality" has been tightened and is now to be
understood as only basic notions of justice and morality i.e., such notions as
would shock the conscience of the Court as understood in Associate Builders v.
Delhi Development Authority (2015) 3 SCC 49 : (AIR 2015 SC 620). The main
object of the amendment of 2015 is to speed up the arbitration process and to
minimize the intervention of the Courts which would ultimately ease doing
business in India.
56. BECAUSE,
the
Amendment of 2015 clearly defines the term public policy of India and has
introduced a new ground, namely Section 34(2A) for setting aside domestic
arbitral awards on the ground of patent illegality. This ground will be
applicable only to arbitrations taking place in India and not to International
Commercial Arbitrations as can be make out from the wording of the section
which says “other than International commercial arbitration.
57. BECAUSE,
In
one of its earlier decisions in Gherulal Parekh v. MohadeodasMaiyain AIR
1959 SC 781, the Hon’ble Supreme Court gave a narrow interpretation of public
policy. It held that within public policy of India, lay certain determinate
specified heads and that it would not be prudent to begin search for new heads.
However, in Central Inland Water Transport Corp Ltd v Borjo Nath Ganguly,
the Hon’ble Supreme Court promoted a wider stance by interpreting the term
public policy on the pillars of public conscience, public good and public
interest.
58. BECAUSE,
the
Petitioner states that such awards, without an iota of reasoning, are rendered
patently illegal and also in violation of public policy of India. On this
basis, it was submitted that this was a sufficient ground under Section 34 of
the Arbitration Act, for setting aside the impugned awards.
59. BECAUSE,
The
MSME Act was introduced with the purpose of facilitating the promotion and
development of micro, small and medium enterprises as well as ensuring their
competitiveness. It aims at ensuring timely and smooth flow of credit to such
enterprises as well as minimizing instances of sickness among them. Further,
the Act itself provide statutory remedy of appeal under Section 19 of the MSME
Act.
60. BECAUSE
, In
support of the above contentions, Appellant relied upon various judgments of
Apex Court in the cases of Tirupati Steels vs. Shubh Industrial
Component and Ors. reported in (2022)7 SCC 429, Modern
Industries Versus Steel Authority of India Limited and Others reported
in (2010) 5 SCC 44: 2010 LAWPACK(SC) 48090, United Bank of India Versus
SatyawatiTondon and Others reported in (2010)8 SCC 110: 2010
LAWPACK(SC) 48508, Snehadeep Structures Private Limited Versus
Maharashtra Small Scale Industries Development Corporation
Limited reported in (2010)3 SCC 34: 2010 LAWPACK(SC) 47743: 2010(1)
R.A.J. 532, Goodyear India Limited Versus Norton Intech Rubbers Private
Limited and Another reported in (2012)6 SCC 345: 2012
LAWPACK(SC) 51351, Gujarat State Disaster Management Authority Versus
Aska Equipments Limited reported in (2022)1 SCC 61: 2021 LAWPACK(SC)
65628, Sri Paravathi Parmeshwar Cables and Others Versus
Andhra Pradesh Transmission Corporation Limited and Another reported
in (2013)10 SCC 693: 2012 LAWPACK(SC) 51904: 2013(1) R.A.J. 148 and Authorized
Officer, State Bank of Travancore and Another Versus Mathew K.C. reported
in (2018)3 SCC 85: 2018 LAWPACK(SC) 60356. Reliance is also placed upon judgment
of this Court in Sanghi Industries Ltd. and Anr.
Verus Micro Small Enterprises Facilitation
Council and Anr. (SBCWP No.988/2018) which has been upheld
by Division Bench also in DBSAW No.591/2018 titled as Sanghi Industries
Ltd. and Anr.
Verus Micro Small Enterprises Facilitation
Council and Anr.. Relying upon the same, the Appellant submits
that the MSME Act is a special and beneficial piece of
legislation and has an overriding effect over other laws, in terms of
Section 24 of MSME Act; and Section 15 of the MSME Act imposes a
liability on buyer to make timely payment and Section 16 of the MSME
Act imposes heavy interest liability for the delay. It is submitted that when
provisions of Section 18 and 19 of the MSME Act prescribe a
statutory and specific mechanism, the same cannot be bye passed. In
the present facts and circumstances, on merits as well as as per statutory
mechanism, the learned Arbitrator has, legally and factually,
committed an error in entertaining the the two issues and by relaxing
the provision of MSMED Act and Indian Contract Act, is is contrary to the above
cited judgments of Apex Court.
61. BECAUSE,
It
is only when the interpretation of contractual provisions is patently
unreasonable or perverse, or contradictory to well settled principles governing
interpretation of contracts, that the court would interfere. Further, it is
equally well settled that an arbitral tribunal being a creature of a contract,
is bound to act in terms of the contract. An award can be said to be patently
illegal where the arbitral tribunal has failed to act in terms of the contract
or has ignored the specific terms of the contract. In this regard reference may
be made to the judgment of the Supreme Court in Indian Oil Corpn. Ltd. v. Shree
Ganesh Petroleum, (2022) 4 SCC 463: 2022 LAWPACK(SC) 66156: 2022(2) R.A.J. 100
wherein it has held as under:
"43. An Arbitral Tribunal being a
creature of contract, is bound to act in terms of the contract under which it
is constituted. An award can be said to be patently illegal where the Arbitral
Tribunal has failed to act in terms of the contract or has ignored the specific
terms of a contract.
44. However, a
distinction has to be drawn between failure to act in terms of a contract and an
erroneous interpretation of the terms of a contract. An Arbitral Tribunal is
entitled to interpret the terms and conditions of a contract, while
adjudicating a dispute. An error in interpretation of a contract in a case
where there is valid and lawful submission of arbitral disputes
to an Arbitral Tribunal is an error within jurisdiction.
45. The Court does
not sit in appeal over the award made by an Arbitral Tribunal. The Court does not ordinarily
interfere with interpretation made by the Arbitral Tribunal of a contractual
provision, unless such interpretation is patently unreasonable or perverse.
Where a contractual provision is ambiguous or is capable of being interpreted
in more ways than one, the Court cannot interfere with the arbitral award, only
because the Court is of the opinion that another possible interpretation would
have been a better one.
62. BECAUSE,
Similar
observations have been made by the Supreme Court in UHL Power Co. Ltd. v. State
of H.P., (2022) 4 SCC 116: 2022 LAWPACK(SC) 65937: 2022(1) R.A.J. 193; Dyna
Technologies (P) Ltd. v. Crompton Greaves Ltd., (2019) 20 SCC 1: 2019
LAWPACK(SC) 63557: 2020(1) R.A.J. 33; State of Chhattisgarh v. SAL Udyog (P)
Ltd., (2022) 2 SCC 275: 2021 LAWPACK(SC) 65698: 2021(6) R.A.J. 154; ParsaKente
Collieries Ltd. v. Rajasthan Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC 236:
2019 LAWPACK(SC) 62577: 2019(5) R.A.J. 1 and South East Asia Marine Engg. &
Constructions Ltd. (SEAMEC LTD.) v. Oil India Ltd., (2020) 5 SCC 164: 2020
LAWPACK(SC) 64119: 2020(3) R.A.J. 234.
63. BECAUSE,
it
is a settled law that only where the interpretation of the contractual
covenants is plainly unacceptable, or contradictory to well settled principles
governing interpretation of contractual covenants, or the interpretation
accorded by the Arbitral Tribunal to a contractual covenant would be contrary
to other covenants of the same contract, that the Section 34 Court can
interfere.
64. BECAUSE,
It
is a well settled principle of contractual interpretation that if a contractual
provision is unambiguous, the same has to be given effect to. Only if there is
any ambiguity, will it be permissible to resort to internal aids to resolve the
ambiguity. Only if internal aids prove insufficient, recourse to external aids
is permissible. In Pandit Chunchun Jha v. Sheikh Ebadat Ali (supra), it has
been held as under:
"6.
The first is that the intention of the parties is the determining factor: see
Balkishen Das v. Legge. But there is nothing special about that in this class
of cases and here, as in every other case where a document has to be construed,
the intention must be gathered, in the first place, from the document itself.
If the words are express and clear, effect must be given to them and any
extraneous enquiry into what was thought or intended is ruled out. The real
question in such a case is not what the parties intended or meant but what is
the legal effect of the words which they used. If, however, there is ambiguity
in the language employed, then it is permissible to look to the surrounding
circumstances to determine what was intended.
65. BECAUSE,
A
document, as is well known, must primarily be construed on the basis of the
terms and conditions contained therein. It is also trite that while construing
a document the court shall not supply any words which the author thereof did
not use.
66. BECAUSE,
The
primary rule of construction of a document is the intention of the executants,
which must be found in the words used in the document. The question is not what
may be supposed to have been intended, but what has been said. We need to carry
on the exercise of construction or interpretation of the document only if the
document is ambiguous, or its meaning is uncertain. If the language used in the
document is unambiguous and the meaning is clear, evidently, that is what is
meant by the executants of the document. Contemporary events and circumstances
surrounding the execution of the document are not relevant in such situations.
67. BECAUSE,
An
Arbitral Tribunal being a creature of contract, is bound to act in terms of the
contract under which it is constituted. An award can be said to be patently
illegal where the Arbitral Tribunal has failed to act in terms of the contract
or has ignored the specific terms of a contract.
68. BECAUSE,
If
the meaning of the word or phrase or sentence is clear, extrinsic evidence is
not admissible. It is only when there is latent ambiguity that extrinsic
evidence in the shape of interpreting statement in which both parties have
concurred should be admissible. The parties themselves might not have been
clear as to the meaning of the word or phrase when they entered into the
contract. Unanticipated situation might arise or come into the contemplation of
the parties subsequently which would sharpen their focus and any statement by
them which would illuminate the darkness arising out of the ambiguity of the
language should not be shut out. In the case of an ambiguous instrument, there
is no reason why subsequent interpreting statement should be inadmissible.
G. NON-FILING
PARA
69.
The Appellant fairly states before this Hon’ble Court, that
inadvertently, the present Appeal was initially filed, within time, before the
Ld. District and Session Court, West District and the same was marked to the
Court of District Judge-04 vide Case bearing Number ARBTN 9/24, in which notice
and reply was also received, however, the said petition was withdrawn to be
filed before this Hon’ble Court and the Appellant is also preferring a separate
application under the provision of Limitation Act as the petition before the
Ld. District Court West District was
contested by the Appellant with due diligence, in good faith and under a
bonafide mistake.
70.
The present Appeal is being filed within the
period of limitation as prescribed by the Provisions of the Act and within the
time frame as provided under the Arbitration as well as the MSMED Act, however
as mentioned supra, a separate application is also filed alongside the
present petition.
71.
That the Requisite Court Fee in accordance with
the Valuation in the Statement of Claim has been affixed with the Present
Appeal. It is stated that 34(5) of Arbitration Notice compliance has been dealt
with.
72.
The Appellant reserves its right and otherwise
craves liberty and indulgence of this Hon’ble Court to file such other
documents, applications and affidavits to add to and supplement it’s present
Appeal.
73.
This appeal is made bonafide and in the
interest of justice.
74. PRAYER
It is, therefore, most respectfully prayed that this
Hon’ble Court may be pleased to
A. Allow
the Instant Appeal and Set Aside the Impugned Order which is under Challenge
qua the amount as granted by the LD. Arbitrator.
B. Pass
such other and further orders as this Hon’ble Court may be deem just and fit in
the facts and circumstances of the present matter.
APPELLANT
Through
Xxxxxx
Xxxxxx
Xxxxxx
XXX
New
Delhi
xxxxxx
BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/S
XXXXXX … APPELLANT
VERSUS
M/S
XXXXXX …
RESPONDENT
AFFIDAVIT
Affidavit of Mr. Xxxxxx, Partner of M/s Xxxxxx,
having their address at Xxxxxx, do hereby solemnly affirm and states as under:-
1. I am
the Authorized representative/Partner of the Appellant Company in the above
Suit and competent to swear this Affidavit.
2. I say
that I have signed, verified and instituted the present Appeal for and on
behalf of the deponent.
3. I say
that the contents of paragraphs of the accompanying Appeal under section 19 of
MSME Act read with section 34 sub clause 2 of the Arbitration and Conciliation
Act, have been drafted by my counsel as per my instructions and the contents of
the same have been duly read and understood by me and after fully understanding
the contents of the same, I hereby state that the facts stated therein are all
true and correct to my knowledge.
DEPONENT
I, Xxxxxx, the deponent named
hereinabove, solemnly affirm and verify that the contents of the above
Affidavit are true and correct to my knowledge. No part of it is false, and
nothing material has been concealed therefrom.
Verified at Delhi on this ___day of XXXXXX
DEPONENT
BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/S
XXXXXX …
APPELLANT
VERSUS
M/S
XXXXXX …
RESPONDENT
STATEMENT
OF TRUTH
Under
the First Schedule, Order VI-Rule 15A and Order XI Rule 3
Affidavit
of Mr. Xxxxxx, Partner of M/s Xxxxxx, having their address at Xxxxxx, do hereby
solemnly affirm and states as under:-
1.
I
am the Authorized representative/Partner of the Appellant Company in the above
Suit and competent to swear this Affidavit.
2.
I
am extremely conversant with the facts of the case and have also examined all
relevant documents and records.
3.
I
say that the statements made in____paragraphs are true to my knowledge,
statements made in _ _ _ _ _ paragraphs are based on information received that
I believe to be correct, and statements made in—-—paragraphs are based on legal
advice.
4.
I
say there is no false statement or concealment of any material fact, document,
or record. I have included information relevant to the present Suit under
Reply, which is based on records.
5.
All
the documents in my power, possession, control, and custody pertaining to the
facts and circumstances of the proceedings initiated against me have been
disclosed. Copies thereof are annexed to the Suit, and the Deponent prefers an
Application under the Provision of Order XI Rule 1(4) as amended by the
Commercial Courts, Commercial Appellate Division of the High Courts Act, 2015,
read with Section 151 of the Code of Civil Procedure, 1908
6.
The
above-mentioned Suit consists of __ pages, each of which I have duly signed.
7.
The
Annexures hereto are true copies of the documents I referred to and relied
upon.
8.
I
am aware that for any false statement or concealment, I shall be liable for
action taken against me under the law for the time being in force.
(DEPONENT)
VERIFICATION:
I,
Xxxxxx, the deponent named hereinabove, solemnly affirm and verify that the
contents of the above Affidavit are true and correct to my knowledge. No part
of it is false, and nothing material has been concealed therefrom.
Verified at Delhi on this ___day of XXXXXX
DEPONENT
BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/S
XXXXXX … APPELLANT
VERSUS
M/S
XXXXXX …
RESPONDENT
INTERIM
APPLICATION FOR ON BEHALF OF THE APPLICANT/APPELLANT UNDER THE PROVISION OF
SECTION 5 READ WITH SECTION 14 OF THE LIMITATION ACT TO CONDONE THE ______ DAYS
OF DELAY IN FILING OF THE PRESENT APPEAL BEFORE THIS HON’BLE COURT
MOST RESPECTFULLY
SHOWETH
1.
The Appellant before
this Hon’ble Court prefers the present application in the afore-mentioned,
which is filed under the provision of Section 19 of MSMED Act, 2006 read with
the Section 34(2) of the Arbitration and Conciliation Act, 1996, for short “Arbitration
Act” and with Section 151 of the Code of Civil Procedure Code, 1908, for
short “Civil Code”, whereby, the Appellant is challenging the Order dated XXXXXX
, for short “Impugned Order” on a limited aspect, of the fact that the
Respondent was directed to pay a sum of INR XXXXXX/- Inclusive of Interest
alongside the Litigation Cost against a claim of INR XXXXXX /- inclusive of
interest as filed by the Appellant before the Learned Arbitrator in the
Statement of Claim under the relevant provision of Section 5 read with Section
14 of the Limitation Act, 1963.
2.
The
Appellant/Applicant inadvertently filed the present Appeal before the
Ld. District and Session Judge, West District, Tis Hazari Courts, on XXXXXX i.e.,
within the period of Limitation as prescribed under the Ambit of Arbitration
and Conciliation Act, 1996, as amended from time to time, and the Ld. District
Judge-04 vide Order date XXXX , pleased to issue Notice qua the same. The
Copies of the Order as passed are appended alongside Annexure A-1 Colly.
3.
The
Appellant/Applicant instituted the appeal before Respondent, preferring a
Section 34 Petition before the Ld. District Judge Commercial Court-04 Central
Delhi, which was subsequently filed by Respondent. However, the
Appellant/Applicant reserves the right to dispute the jurisdiction;
however,with an intent to finally adjudicate the said issue on merits, the
Appellant/Applicant vide order dated xxxxxx, pleased to withdraw the said
Appeal from the Ld. District Judge-04, West District Tis Hazari Courts New
Delhi, with liberty to file the Appeal before this Hon’ble Court. The Said
Appeal was subsequently filed immediately XXXXX , before this Hon’ble
Commercial Court.
4.
That there is no delay; however, as an
abundant precaution, the Applicant prefers the present delay application under
the provision of Section 5 read with Section 14 of the Limitation Act, seeking
condonation of 183 Days.
5.
It
is a settled proposition of Law, as even held down by the Hon’ble Supreme
Court, that Section 14 of the Limitation Act would apply to the proceedings
under Section 34 of the Arbitration and Conciliation Act, 1996 if the petition
under Section 34 (at the first instance) were filed within time.
6.
The
Hon’ble Supreme Court in Oriental Insurance XXXXXX [1]
dealt with an issue “whether the presentation of the petition before the Judge,
Jodhpur, should be considered as a fresh petition and the explanation for the
entire period from the original limitation period i.e., from the date of the
award is to be considered for the purpose of condonation of delay for
prosecuting in an alternate jurisdiction, while considering the application
under Section 14 of the Act.” And held as under
Though
the judgment in Simplex Infrastructure Ltd. vs. Union of India, (2019) 2 SCC
455 was relied upon to contend that Section 5 of the Limitation Act has no
application to a petition challenging the arbitral award under Section 34 of
the Act, 1996, the bench noted that the same judgment indicated that Section 14
of the Limitation Act is applicable to an application submitted under Section
34 of the Act, 1996 seeking for exclusion of certain period if the application
under Section 34 of the Act, 1996 is at the first instance filed within the
limitation period provided under Section 34(3) of the Act, 1996. While allowing
the appeal, the bench observed:
"In
the instant case as already indicated above the condonation of delay sought is
not for filing the petition under Section 34 of the Act, 1996 for the first
time. The petition filed under Section 34 of the Act, 1996 at Jaipur was within
the period of limitation and the delay regarding which explanation is put forth
is for the period of 8 days in re-presenting the petition beyond the date fixed
after it was returned under Order 7 Rule 10 of the Civil Procedure Code.
Therefore, in that circumstance even if the term "sufficient cause"
as contained under Section 5 of the Limitation Act is taken note, in the
present facts the same is not with reference to petition under Section 34 of
Act, 1996 for condonation of delay beyond the period prescribed under Section
34(3) of the Act, 1996. Though that be the position what is necessary to be
taken note herein is that the application filed for excluding the time is under
Section 14 of the Limitation Act. In addition to the very decisions cited above
indicating that Section 14 of the Limitation Act would be applicable to the
proceedings under Section 34 of the Act, 1996 subject to the petition under
Section 34 being filed within time, the learned counsel for the appellant has
also relied upon the decision in the case of M/s Consolidated Engineering
Enterprises vs. The Principal Secretary, Irrigation Department & Ors.
(2008) 7 SCC 169 wherein the same position is reiterated
7.
Recently,
the Hon’ble Delhi High Court in National Seeds Corporation versus Ram Avtar
Gupta[2]has
held that Section 14 of the Limitation Act, which provides for exclusion of
time consumed in civil proceedings initiated before a Court not having the
jurisdiction, applies to proceedings under Section 34 of the A&C Act,
whereby the Analysis of the Hon’ble Court was as follows
Analysis
by the Court
The
Court thoroughly analyzed the case in light of relevant Supreme Court
judgments. It acknowledged the undisputed chronology of events, wherein the
petitioners challenged the award through a Section 34 petition within the
stipulated 3-month period. The Court then examined the diligence displayed by
the petitioners in their pursuit of legal remedies. Notably, the petitioners'
initial filing was under the genuine impression that the jurisdictional
threshold was met. The Court observed that this filing was done well within the
statutory period.
Considering
the arguments put forth by both parties, the Court addressed the respondent's
contention about the exclusion of the limitation period under Section 14 of the
1963 Act. The Court found that the petitioners fulfilled the conditions set by
the Supreme Court in 'Suryachakra Power Corporation Limited v. Electricity
Department Represented by its Superintending Engineer, Port Blair and Others,
(2016) 16 SCC 152', establishing their diligent and good faith efforts.
The
respondent's opposition to the Section 14 benefit was countered by the Court,
which emphasized that the petitioners' actions were not indicative of
unnecessary delay. The Court also examined the respondent's arguments
concerning the condonable period under the proviso to Section 34(3). The Court
clarified that the petitioners' reliance on the Supreme Court's exclusion order
(Re: Cognizance for Extension of Limitation) and Section 14 allowed their
filing to be well within the extended limitation period.
The
Court refuted the respondent's claim that the extension only applied to the
limitation period and not the condonable period, stating that irrespective of
this interpretation, the petitioner's filing on XXXXXX was within the
extended period XXXXXX In conclusion, the Court held that the present
petition was filed within the limitation period and granted the application,
disposing of the matter.
8.
That
the Applicant states that the Applicant, bonafidely, filed the Petition before
the District and Session Judge, West District instead of filing it under the
purview of Section 10(3) of the Commercial Act, 2015 before the Ld. Commercial
Courts. The Notice was issued and also the Reply was filed and due to which,
the Applicant had to be spend 183 Days i.e., from Filing of the Petition till xxxxxx
and thereafter the Applicant had filed the Section 34 Petition before this
Hon’ble Court.
9.
That the Appellant states that the Appeal of the
Appellant is filed within the time and there is no delay, however as an
abundant precaution, owing to the Objection as raised by the Respondent, the
Appellant is preferring the Present Application condoning the delay of 183 Days
if any and the delay if any has been caused on the pretext of the reasons as
stated in the above paragraph of the Petition.
10. It is stated
that this application is bonafide and in the interest of justice and no
prejudice shall be caused to Respondent if the Present Application is allowed
and the matter be heard on merits.
11. PRAYER
In the light of the foregoing submissions and circumstances of
the case, it is most humbly prayed that this Hon’ble Court be pleased to:
A.
Allow the Present Application and Condone the Delay of 183 Days
in filing of the Present Appeal &
B. Pass
such other and further orders as this Hon’ble Court may be deem just and fit in
the facts and circumstances of the present matter.
APPELLANT
Through
XXXXX
XXXXX
XXXXX
XXX
New
Delhi
XXXXXX
BEFORE
THE HON’BLE DISTRICT JUDGE COMMERCIAL COURTS, CENTRAL DISTRICT, TIS HAZARI
COURTS AT NEW DELHI
O.M.P
COMM _________ OF 2024
IN
THE MATTER OF
M/S
XXXXXX … APPELLANT
VERSUS
M/S
XXXXXX …
RESPONDENT
AFFIDAVIT
Affidavit of Mr. Xxxxxx, Partner of M/s Xxxxxx,
having their address at Xxxxxx, do hereby solemnly affirm and states as under:-
1. I am
the Authorized representative/Partner of the Appellant Company in the above
Suit and competent to swear this Affidavit.
2. I say
that I have signed, verified and instituted the present Appeal for and on
behalf of the deponent.
3. I say
that the contents of paragraphs of the accompanying Application, have been
drafted by my counsel as per my instructions and the contents of the same have
been duly read and understood by me and after fully understanding the contents
of the same, I hereby state that the facts stated therein are all true and
correct to my knowledge.
DEPONENT
VERIFICATION:
I, Xxxxxx, the deponent named
hereinabove, solemnly affirm and verify that the contents of the above
Affidavit are true and correct to my knowledge. No part of it is false, and
nothing material has been concealed therefrom.
Verified at Delhi on this ___day of XXXXX
DEPONENT