BEFORE SH XXXXXX, LD. ARBITRATOR; DISTRICT JUDGE (RETD.),
DELHI INTERNATIONAL ARBITRATION CENTRE (DIAC)
DELHI HIGH COURT, NEW DELHI
CASE REF. NO. DIAC/XXXX/01-20**.
IN THE MATTER OF:-
XXXXX : CLAIMANT
VERSUS
XXXXX :RESPONDENTS
D.O.H.:-______ 20**
REPLY ON BEHALF OF THE CLAIMANT TO THE COUNTER CLAIM FILED BY
THE RESPONDENT.
MOST RESPECTFULLY SHOWETH
:-
PRELIMINARY OBJECTIONS:-
1. That
the allegations, submissions, contentions in the counter claim raised by the
respondent are untenable, false, bogus and are denied. No sums are due and
owing to the respondent as claimed or otherwise. The respondent is obfuscating
issues to mischievously avoid his liabilities.
2. That
the Counter Claim raised by the Respondent in the present proceedings is
without any merit, an afterthought and has been raised as a counter blast to
the Claim Petition filed by the Claimant. It is a matter of fact that no such
Counter Claim was ever raised prior to the present proceedings by the
Respondent against the Claimant. The same deserves to be rejected on this
ground alone.
3. That
the present claim has been raised under the provisions of the Contract which
deals with imposition of Liquidated Damages. It is stated that the counter
claim has been raised completely in contravention of the legal provisions
required to be followed for raising such a claim and the same is also against
the relevant provisions of the Contract. Any claim raised by the Respondent
under this provision of the Contract is liable to be rejected on this ground
alone.
REPLY ON MERITS:-
1. That the contents of para 1 of the counter claim are
reiterated, hence, matter of record. It is submitted that the present counter
claim not signed and filed by the competent person of the respondent company.
2. That the contents of para 2 of the counter claim are
absolutely wrong, incorrect and reiterated, hence specifically denied. It is
denied that the Respondent issued a Work Order dated 17.05.2022 in favour of
the Claimant for construction of warehouse at XXXXX, Delhi, India, the terms of
the Work Order inter alia envisaged that the Claimant would be
responsible for all material, labour, tools, tackles and construction
machinery. It is further denied that the Respondent was obligated to supply
concrete and steel to the Claimant free of cost as per the terms of the
Contract. It is further denied that the Claimant was liable to finish the
construction of the project by 24.11.2022 in terms of the contract, during the
currency of the Work Order following disputes arose between the parties.
a. That the contents of sub para a) of the counter claim are
absolutely wrong, incorrect and reiterated, hence specifically denied. It is
denied that the terms of the Work Order unequivocally stipulated that the
construction of the warehouse building was to be completed by 24.11.2022,
however, the Claimant miserably failed to adhere to the aforesaid timeline for
one frivolous reason or another and demanded extension of timelines from the
Respondent to cover up its failures. It is further denied that the Respondent
granted several extensions to the Claimant and accommodated the Claimant as
much as possible until it became abundantly clear that the Claimant would be
unable to execute the project. It is further denied that therefore, vide email
dated 22.12.2022, the Respondent granted one final extension to the Claimant
till 20.02.2022. It is further denied that as on 20.02.2022, the Respondent had
only completed 30% of the total value of the Work Order and 70% still remained
to be executed, therefore, the Respondent was constrained to terminate the Work
Order vide notice dated 21.02.2022 owing to abject failures of the Claimant to
execute the project in a time bound manner. Any allegation to the contrary
being raised by the Respondent is totally false and incorrect.
b. That the contents of sub para b) of the counter claim are
absolutely wrong, incorrect and reiterated, hence specifically denied. It is
denied that claimant not only failed to complete the construction within the
timelines but also failed to efficiently undertake the construction of the
warehouse as the entire building is vitiated with various defects which have
been duly brought to the knowledge of the Claimant vide various emails. It is
further denied that as per the terms of the Work Order the Claimant is bound to
rectify the defects pointed out by the Respondent and the work cannot be deemed
completed until the defects have been rectified by the Claimant at its own cost
to the satisfaction of the Respondent. Any allegation to the contrary being raised by the Respondent
is totally false and incorrect.
c. That the contents of sub para c) of the counter claim are
absolutely wrong, incorrect and reiterated, hence specifically denied. It is
denied that insufficient manpower became recurrent feature throughout the
execution of the project, as per the terms of the contract, the arrangement and
deployment of adequate labour/ manpower at site was within the scope of the
Claimant. It is further denied however, the Claimant failed to deploy adequate
manpower at site which further contributed to huge delays in progress of the
project. It is further denied that the Respondent, vide several emails
requested the Claimant to deploy adequate labour at site, however the Claimant
turned a deaf ear to the requests of the Respondent. Having not done so, the
Respondent is estopped from raising such false and frivolous allegations at
this point of time against the Claimant.
3. That the contents of para 3 of the counter claim are
absolutely wrong, incorrect and reiterated, hence specifically denied. It is
denied that despite bringing the aforesaid facts and circumstances to the
knowledge of the Claimant vide several emails, the Claimant instead of
effecting any change in the progress of the work, resorted to committing
illegal activities at the site viz. manhandling the project manager of the
Respondent for which the Respondent was constrained to file a police complaint.
It is further denied that therefore, the Respondent was left with no other
option but to terminated the Work Order dated 17.05.2022 vide notice dated
21.02.2022. In any case these
allegations have no bearing on the counter claim raised by the present
Respondent.
4. That the contents of para 4 of the counter claim are
absolutely wrong, incorrect and reiterated, hence specifically denied. It is
denied that due to the aforesaid failures of the Claimant to execute the
project in adherence to the terms of the Work Order, the Respondent has
incurred huge losses which the Claimant is liable to compensate. In any case
these allegations have no bearing on the counter claim raised by the present
Respondent.
That
the reply to counter claims are as under;-
1. That the contents of para 1 of the counter claim-1 delay
compensation are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that the construction of the warehouse was to be completed
by 24.11.2022 as per the terms of the Work Order dated 17.05.2022, however, the
Claimant miserably failed to adhere to the timelines envisaged in the Work
Order and consequently requested the Respondent for extension of timelines. It
is further denied that the Respondent extended all the cooperation to the
Claimant and duly extended the timelines so as to accommodate the Claimant in
covering up its delay, however, the Claimant breached the extended timelines as
well which has led to the Respondent incurring huge losses. It is further
denied that the parties vide a meeting held on 14.10.2022 and by way of an
email of even date mutually agreed that if the Claimant fails to adhere to the
timelines then a genuine pre estimate damage/compensation would be payable by
the Claimant to the tune of 10% of the final project cost. It is further denied
that therefore, the Respondent is claiming 10% delay compensation on the total
amount of work orders amounting to Rs XXXXX/- (Rupees in words Only). The
failure of the Respondent to pay the amounts due to the Claimant are a subject
matter of the claims raised by it before the Hon'ble Arbitrator and are
required to be paid by the Respondent.
2. That the contents of para 2 of the counter claim-2 cost for
completion of remaining work are absolutely wrong, incorrect and reiterated,
hence specifically denied. It is denied that since the Claimant failed to
complete the construction of the warehouse, the Respondent was constrained to
complete the remaining work at its own cost and for that purpose the Respondent
was issued a separate work order dated 23.03.2023 to another contractor,
namely, S.S. Developers and Contractors for completion of the remaining work
left incomplete by the Claimant and for rectification of defects for an amount
of Rs. XXXXX/-. It is further denied that the Claimant is liable to reimburse
the said amount to the Respondent in terms of the Contract. The contents of this para have got no relevance to the
counter claim.
3. That the contents of para 3 of the counter claim-3 refund of
excess amount are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the total contract value of all the
contracts amounted to Rs. XXXXX/-, the Claimant has only raised bills amounting
to Rs XXXXX/- upon the Respondent which amounts to only 32% of the total
contract. IT is further denied that the Respondent has made total payment of Rs
XXXXX/- to the Claimant, therefore, the Claimant is in receipt of excess
payment made by the Respondent to an extent of Rs XXXXX/- after taking into
account all the tax invoices and Performa invoices. Claimant is liable to
refund the excess amount of Rs XXXXX/- to the Respondent along with 18%
interest. The failure of the Respondent to pay the amounts due to the Claimant
are a subject matter of the claims raised by it before the Hon'ble Arbitrator
and are required to be paid by the Respondent.
It is submitted that the respondent is
not entitled to get any relief by way counter claim from the Hon’ble Sole Arbitrator.
Prayer clause along
sub-paras of the counter claim are absolutely wrong and specifically denied.
The respondent is not entitled to the relief claimed for.
That in the aforesaid facts and circumstances of the case,
it is most respectfully prayed that the Hon'ble Arbitrator may be pleased to
award the claims raised by the Claimant in the Claim Petition filed by it.
Further, the Hon'ble Tribunal is requested to reject the counter claim in its
entirety, which has been raised by the Respondent in its Statement of Counter
Claim. The above award may be passed in favour of the Claimant with costs
against the Respondent.
Pass such further order or
orders as this Hon’ble Tribunal may deem fit and proper of the facts and
circumstances of the case, in the interest of justice.
It is prayed
accordingly.
CLAIMANT
DELHI THROUGH
DATED
XXXXX (Advocate)
Counsel for Claimant
Off.: XXXXX
XXXXXX
Mob. No.+91XXXXXX
Email: XXXXXX
BEFORE SH. XXXXXX ARBITRATOR; DISTRICT JUDGE (RETD.),
DELHI INTERNATIONAL ARBITRATION CENTRE (DIAC)
DELHI HIGH COURT, NEW DELHI
CASE REF. NO. DIAC/XXX/01-20**.
IN THE MATTER OF:-
XXXXX : CLAIMANT
VERSUS
XXXXX :RESPONDENTS
AFFIDAVIT
Affidavit
of Mr. XXXXX aged about ___ years, Director / AR of XXXXX, do hereby solemnly
affirm and declare as under:-
1. That I, the AR / Director of
the Claimant company in the above noted case and am fully conversant with the
facts and circumstances of the case and competent to swear this affidavit.
2. That the accompanying reply
to the counter claims has been drafted under my instructions, which has been
read and understood by me and I say that the contents of the same are true and
correct.
DEPONENT
VERIFICATION :-
Verified at Delhi on this ____, day of April, 2024 that the
contents of paras of the above affidavit are true and correct to my knowledge.
No part of it is false and nothing material has been concealed therefrom.
DEPONENT