BEFORE THE SOLE ARBITRATOR xxxxx ; xxxxx, xxxxx
Â
Arbitration Case No. ____ OF
2016.
In the matter of Arbitration between:
Â
M/S
xxxxx
                                      CLAIMANT
VERSUS
xxxxx                           RESPONDENT
Â
REPLY ON
BEHALF OF THE CLAIMANT TO THE COUNTER CLAIM FILED BY THE RESPONDENT.
Â
MOST RESPECTFULLY SHOWETH
:-
Â
PRELIMINARY
OBJECTIONS:-
Â
1.      That the allegations, submissions,
contentions in the counter claim raised by the respondent are untenable, false,
bogus and are denied. No sums are due and owing to the respondent as claimed or
otherwise. The respondent is obfuscating issues to mischievously avoid his
liabilities.
Â
REPLY TO PRELIMINARY SUBMISSIONS
1-2.   That the contents of paras 1-2 of the preliminary
submissions are wrong and denied. It is denied that the claim filed by the
claimant is totally false, baseless, vague and is based upon fake and forged
bills and upon the bills which pertain to the work which was never assigned to
the claimant by the respondent.
Â
3.      That the contents of para 3 of the preliminary submissions are
wrong and denied. It is denied that the claimant has filed three separate
claims against three different sister concerns of the respondent company and
has intermingled the bills of work of these companies in these claims thereby
rendering these claims as suspicious. It is submitted that claim of the
claimant is only concerned to M/s xxxxx & is not intermingled with any
other concern of M/s xxxxx . Although, the claimants are in legal tussle of
receivable payments with other companies of M/s xxxxx separately.
Â
4.      That the contents of para 4 of the preliminary submissions are
wrong and denied. It is denied that the whole claim of the claimant is based on
such irrelevant and baseless invoices which clearly prove the falsity of the
claim of the claimant and the malafide intentions of the claimant to mislead
the Tribunal and therefore the claim of the claimant is liable to be dismissed. The Invoice no. xxxxx is explainable
legitimate the claimant is are enclosing herewith the copy of invoice as cited,
duly verified by the resident project manager of M/s xxxxx– Mr.xxxxx . Also, be
point out that P.O. no. being mentioned in the referred invoice i.e. xxxxx /
Mor-330 is in accordance to P.O. Further, claimant has also received the ’WCT’
Form bearing no. xxxxx dtd xxxxx against the mentioned invoice, which clarifies
he acceptance of invoice by M/s xxxxx . Similarly, invoice no. MI/SER/xxxxx  being denied by respondent is legitimate in
all respect. The copy of P.O. vide ref. no. xxx/xxx /xxx/xxx/xxx dtd. xxxxx
pertaining to the said invoice and also referred in the same invoice is being
enclosed for reference of the respondent. It is submitted that Invoice xxxx/xx /xx/xxx
are legitimate and in accordance to the issued Purchase Order. There had been a
discrepancy in noting of P.O. number in the referred invoice but it was purely
typology error and has not discrepancy in relation to statutory such as Party
Name, values or taxes. The material was dispatched and receipted at site and in
binding M/s xxxxx has also issued us ‘C’ Form bearing no. xxxxx dtd xxxxx.
Henceforth, the invoices are legitimate.
Â
REPLY ON
MERITS:-
1.      That the contents of para 1 of the counter
claim are reiterated, hence denied. It is submitted that the present counter
claim not signed and filed by the competent person of the respondent company.
Â
i).     That the contents of para 1 of sub para
(i) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the respondent had obtained the services
of claimant vide various purchase/work orders but the claimant's work/services
were very poor from the very inception, Claimant's way of working was of
sub-standard and not up to the mark as per the established standards of the
industry. It is further denied that the material supplied by the Claimant was
also below standard and not in conformity to the purchase order issued to the
Claimant. It is also denied that as per the Purchase order issued to the
Claimant, the Claimant \ had to supply Structured Steel of SAIL/JINDAL/TATA \
BRANDS but the Claimant failed to adhere this and instead supplied this
material of local/other unspecified brands. It is further denied that the claim
of the Claimant is based on unverified bills/quantity of material supplied
though it was mandatory for the Claimant to get the bills of material &
services verified from the project manager of the respondent but the claimant
failed to comply the said requirement. It is further denied that this issue of
supply of local/other unspecified brand material was raised by the respondent
and after a lot of persuasion, claimant admitted the fact of supply of material
of different brand than agreed in P.O. and further agreed to issue credit note
@ Rs.xx per Kg. but never credited this amount to Respondent. It is further
denied that the respondent is entitled to recover an amount of Rs.xxxxx /- on
this account. It is admitted that claimant accepted the credit note of Rs.xxxxx/-.
Â
ii).    That the contents of para 1 of sub para
(ii) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the claimant was bound to get the material inspected from the authorized representative of the Respondent before
dispatch of material as per the "inspection" clause of the Purchase
Order but claimant completely
failed to adhere the same and
supplied the material without affording any opportunity to respondent to
inspect die same. It is further denied that the said inspection was never
waived-off by the respondent in this
way the claimant supplied uninspected sub-standard material to the respondent
which caused huge bearing on the project which in turn harmed the respondent
financially besides causing loss of reputation. The statement is totally
baseless. It would have been complete rejection against the supply of first
consignment to site if the case was no inspection basis. Always there had been
verbal inspection discussions with concerned officials of M/s xxx and due to
urgency of project executions were always asked to dispatch the material at
site. Never ever, neither post receipt of material at site nor in any
communication there had been any concerns of inspection.
Â
iii)Â Â Â Â That the contents of para 1 of sub para
(iii) of the counter claim are absolutely wrong, incorrect and reiterated,
hence specifically denied. It is denied that the claimant failed to supply the material in exact confirmation of the
bills raised by him i.e. the material supplied by him was short as
described/detailed in his invoices. It is further denied that the claimant is
liable to refund the amount equivalent to the value of short quantity which
comes to Rs. xxxxx/-. The matter being represented
in relation to difference in weights is totally false and baseless. The matter
was never brought in knowledge of any Mannschaft personnel, either by e-mail or
even to the site incharge of claimant regarding shortage material supply. The
weighment slips being now annexed by M/s xxxxx is their internal property and
had never been shared / or communicated to the claimant in the past.
Â
iv)Â Â Â Â Â That the contents of para 1 of sub para
(iv) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that
as per the terms and conditions of the purchase order, the claimant had to
supply the complete material within two months of the date of purchase
order but the claimant also failed to supply the material within the stipulated
time frame and whatever material was supplied by him, was
unverified/uninspected & short. It is further denied that the claimant
totally failed to supply the material as per the purchase order which on one
hand delayed the project of the respondent and on other hand also affected the
quality & strength/durability of structures of the project. It is also
denied that as per the Clause 12 of Purchase Order, the respondent is entitled
to recover Liquidated Damages from the claimant to the tune of Rs. xxxxx/-. The
para being raised by M/s xxxx is totally frivolous. The delay in execution of
the project whatever pertained has always been on account of M/s xxxxx
non-payments and irregularities. The same was communicated to them through
various mails that had been annexed in the claim of the claimant.
Â
v)Â Â Â Â Â Â That the contents of para 1 of sub para
(v) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the Respondent asked the Claimant
several times not to supply the sub-standard material and made the Claimant
understand that the said material was to be used in Solid Waste Management
Project which infact was a prestigious project of the Central & State
Government implemented as per the direction of Hon'ble Supreme Court and
therefore the Respondent was not in a position to compromise over the quality
of material used in this project, but the Claimant was not ready to understand
the seriousness of the situation and continued with his hostile attitude. It is
further denied that the respondent also asked the claimant to supply the
complete quantity of material as per the Purchase Order and that too within the
stipulated time frame but to no use. It is also denied that the claimant failed
to supply the complete quantity of material and due to this short fall in
material, respondent had to procure this short material from other vendors that
too on higher rates in the situation of exigency because it was a prestigious project
for the respondent and respondent wanted to complete it at any cost and in this
way the respondent has suffered huge financial losses besides mental
harassment. The para of use of sub standard material is totally baseless. The
use of alternate make of material was agreed upon mutually considering
non-availability of desired makes and keeping in mind the execution intact.
Also, the reduced price of INR xxx/- was result of mutual discussions, as
referred in para no. (i). Â
Â
vi)Â Â Â Â Â That the contents of para 1 of sub para
(vi) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that apart from the purchase order, the
respondent had also entrusted a work order upon the claimant and the said
contract regarding Civil Work was also time bound i.e. time was the essence of
the contract i.e. the claimant was bound to complete the Civil Work within 100
days from the date of work order but the claimant was not able to arrange the
sufficient man power / labour which was necessary to execute the ongoing
project which ultimately harmed the respondent financially besides causing
delay in execution of the project. It is further denied that respondent asked
the claimant several times to improve his working but to no use due to this
continued scenario, work was totally halted at several occasions. It is also
denied that vide email dated xxxxx the respondent requested the claimant to
arrange for a panting team to paint the structured steel before erecting the
same and again reminded vide email dated xxxxx to arrange the team for painting
of steel structure otherwise it will be difficult to paint the structure after
erection but the claimant did not bother to the request of the respondent. The para
being raised by M/s xxxxx is totally frivolous. The delay in execution of the
project whatever pertained has always been on account of M/s xxxxx non-payments
and irregularities. The same was communicated to them through various mails
that had been annexed in claim of the claimant. The delay was purely in
relation to delayed payments from M/s xxxxx end.
Â
vii)Â Â Â That the contents of para 1 of sub para
(vii) of the counter claim are absolutely wrong, incorrect and reiterated,
hence specifically denied. It is denied that due to the deficient work
rendered by the claimant and continues delay in execution of the work, respondent was under constant
pressure to complete the work in time and therefore the respondent warned the
claimant several times to complete the work in time but no fruitful results
emerged and the claimant continued with his hostile attitude towards the
assigned work. It is further denied that it that vide E-mail dated xxxxx, the respondent wrote to the Claimant
"as discussed on telephonic several times and with reference to the
trailing mails for engage of extra team/manpower for the speed up of erection
work, still no response is getting from your side. Kindly note that we have
started the erection work of pre-sorting shed from last month back (inc. all
disputes) but still the work is not completed, your vendor has engaged only 07
persons. As per your working criteria, you are taking one month for completing
one shed, its means we required next 04 months to complete the overall job.
Again requested to please arrange your extra team by today itself at any cost,
for speed up of the work. It is further denied that the respondent again
warned of the same situation vide E-mail dated xxxxx . Further Vide E-mail
dated xxxx, the respondent wrote to the claimant "with reference to the
telephonic discussion with you have regarding the welding of extra based plate
for shed numbers 10, 10a, 14, 14a for structural columns, kindly
arrange the same by today itself otherwise your labour will be sitting idle.
Apart from this, still your new contractor for structural steel erection not
started the work due to lack of hydra, electricity, LPG, oxygen etc. / am not
understanding that how you are managing your contractor. Kindly revert me back
asap." It is also denied that the delay in execution of work &
poor speed of work was further explained to Claimant vide various E-mails, vide
email dated xxxxx, the respondent informed the claimant about not supplying the
balance structure material for final compost section and monsoon shed and
further informed the claimant about the pendency of painting of steel structure
and requested to arrange the team for the same. it is further denied that vide
this mail, the respondent further informed the claimant that erection of
structure for pre-sorting, RDF, inert processing shed was not up to the mark
and about the discontinuation of the work since last 25 days and other problems
regarding the slow pace of the work. It is also denied that vide another email
dated xxxxx , the respondent informed the claimant about the poor work progress,
again vide email dated xxxxx, the respondent reminded about the slow pace of
civil as well as mechanical work which was due to the payment dispute of
claimant with his sub-contractors. It is further denied that vide this email,
the respondent again raised the old issues which the claimant had failed to
resolve despite repeated requests and reminders of the respondent. It is also
denied that the Claimant failed to improve the pace of work resulting into
idling of manpower and this fact is evident from mail dated xxxxx. It is
further denied that due to incomplete supply of material as per purchase order,
delay, poor quality work of claimant and idling of manpower, respondent had to
bear all additional costs pertaining to labour’s wages, rent of hired
machineries administrative cost, etc. etc. on his own, only due to the abovementioned
defaults on the part of the claimant and respondent has suffered to the tune of
Rs. xx Lakhs for above mentioned causes which the respondent is entitled to
recover from the claimant. The para is already replied with in above. Respondent
has referred e-mail dated xxxxx and the claimant replied to para with governed
action on xxxxx (copy enclosed). Likewise, respondent e-mail dated xxxxx was
replied immediately mentioning the pending payments matters (copy enclosed).
Likely, respondent’s email dated xxxxx was replied by claimant after awaiting
until xxxxx, similarly pertaining matter to non payments.
Â
viii)Â Â That the contents of para 1 of sub para
(viii) of the counter claim are absolutely wrong, incorrect and reiterated,
hence specifically denied. It is denied that due to above mentioned
delay in execution of work order substandard work rendered by the claimant the project
of the respondent delayed of more than six months which
includes the time spent in getting the work done/completed from
another vendor. It is further denied that due to this delay of more than 6 months, the respondent could not start the production of Compost & RDF and consequently incurred loss of earnings on account o\ loss of production to the tune
of R.s. xxxxx /- as profit. It is also
denied that the claimant seeks damages for business losses for a period of 1
months only sub sequent to the stoppage of operations by the claimant and states that the same are
actual and directly emerge from the defaults of the claimant. The para is
frivolous and unjustified.
Â
ix)Â Â Â Â That the contents of para 1 of sub para
(ix) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the respondent is also entitled in
recovery liquidated damages in the tune of Rs.xxxxx/- from the claimant for
aforementioned delay caused by claimant as per clause 12 of work order. The para
is frivolous and unjustified.
Â
x)Â Â Â Â Â Â That the contents of para 1 of sub para
(x) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the claimant was legally bound to
deposit labour cess to the government to the tune of 1% of the total value of
work order and purchase order which comes to Rs.xxxxx /- but the claimant
ignored the same despite repeated requests by the respondent. It is further
denied that the respondent itself has to deposit the said labour cess to the
concerned authorities and therefore suffered loss of Rs. xxxxx/- which amount
is legally recoverable from the claimant. It is further denied that the
claimant has also failed to produce any documents with regard to labour
compliances like ESIC/PF/Insurance etc. in utter violations of clause no.8
& 13 of the work order. It is also denied that the claimant has also failed
to produce on record any labour licence in its favour by the competent labour
authorities. The deposit of labour cess is purely M/s xxxxx  liability. The annexure letter referred is
addressed in the name of M/s xxxxx and was never ever brought in knowledge of
claimant ever. Also, there is no reference of the matter in statutory taxes in
the Purchase Order. It would have been virtually impossible for claiamnt– MIIPL
to work at site without labour policy or compliance to statutory like ESI / PF
etc. Neither claimant could have initiated work nor M/s xxxxx could employ such
contractor. Claimant’s sub contractor xxxxx was a resident sub contractor to
M/s xxxxx team on the similar site for various other works and they have
provided all statutories to M/s xxxx and then initiated work on account of
MIIPL. Also, an e-mail dated xxxxx (copy enclosed) pertaining to scanned copy
of workman insurance policy is enclosed.
Â
xi)Â Â Â Â That the contents of para 1 of sub para
(xi) of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the services rendered by the claimant to
other group companies of respondent are also deficient and below specified
standards due to which these group companies have also suffered huge financial
losses besides mental harassment. The claimant has outstanding payments and
statutory with other companies of M/s xxxx Group and they are being trialed in
court separately.
Â
xii)Â Â Â That the contents of para 1 of sub para (xii)
of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. Â It is denied that besides
above mentioned financial losses, Respondent has also suffered on account of
loss of reputation & goodwill, mental & physical harassment etc. solely
due to the lacklustre approach of claimant towards his liabilities entrusted
upon him through purchase/work order and therefore the claimant is liable to
compensate the respondent for all these losses to the tune of Rs. xxxxx/-.
Â
xiii)Â Â That the contents of para 1 of sub para (xiii)
of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that there are numerous defaults/violations
on the part of Claimant due to which the Claimant failed to complete the works
within the stipulated time and further failed to supply the requisite materials
i.e. the Claimant failed in totality to complete the assigned work which have
caused numerous losses to the Respondent as detailed above.
Â
xiv)Â Â Â That the contents of para 1 of sub para (xiv)
of the counter claim are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that despite all the above mentioned facts
regarding the failure of Claimant to properly execute the order of supply &
works, the Respondent has paid an amount of Rs. xxxxx/- to the Claimant till
date and the Respondent is also legally entitled to recover these amounts from
the Claimant
Â
======
4.      That the contents of para 4 of the counter
claim are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that finding no way out and to save its projects, the
respondent had to buy those material / machines from another vendor namely M/s.
xxxx for replacing the defective
material / machines supplied by the claimant, this was a huge financial burden
upon the respondent. It is further denied that debit notes worth Rs.43,38,744/-
were issued to the claimant to compensate the losses suffered by respondent in
purchase of above said material from M/s. xxxxx & other .
Â
5.      That the contents of para 5 of the counter
claim are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that due to the deficient work rendered by the claimant
and continues delay in execution of the work, respondent was under constant
pressure from xxxx. to complete the work in time and therefore the respondent
warned the claimant several times to complete the work in time but no fruitful
results emerged and the claimant continued with his hostile attitude towards
the assigned work.
Â
6.      That the contents of para 6 of the counter
claim are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that the services rendered by the claimant to other group
companies of respondent are also deficient & below specified standards due
to which these group companies have also suffered huge financial losses besides
mental harassment. It is further denied that those losses are yet to be
assessed and shall be brought on record at the earliest.
Â
7.      That the contents of para 7 of the counter
claim are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that due to deficient and delayed work rendered by the
claimant, respondent had to bear all additional costs pertaining to Idling
charges, labour’s wages, rent of hired machineries and administrative cost etc.
etc. on his own, only due to the abovementioned defaults on the part of the
claimant and therefore the claimant is solely liable to compensate the
respondent for that.
Â
8.      That the contents of para 8 of the counter
claim are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that besides above mentioned financial losses, respondent
has also suffered on account of loss of reputation and goodwill, mental and
physical harassment etc solely due to the lackluster approach of claimant
towards his liabilities entrusted upon him through purchase order and therefore
the claimant is liable to compensate the respondent for all these losses.
Â
9.      That the contents of para 9 of the counter
claim are absolutely wrong, incorrect and reiterated, hence specifically
denied. It is denied that as on date, the ledger of the respondent shows a
debit balance of Rs.xxxxx /- i.e. the respondent is entitled to recover Rs.xxxxx
/- from the claimant for which the respondent is filing present counter claim.
Â
10.    That the reply to counter claims are as under;-
Â
A.      That the contents of sub para A of the claim-
ledger balance are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that the respondent is legally entitled to
recover Rs.xxxxx /- being amount due against the claimant as per ledger.
Â
B.      That the contents of sub para B of the claim-idling
charges  are absolutely wrong, incorrect
and reiterated, hence specifically denied. It is denied that Rs.xx Lacs being
amount incurred by respondent against additional costs pertaining to labour’s
wages, rent of hired machineries, administrative cost etc. which the respondent
incurred on account of idling of manpower and machinery due to halt of work on
several occasions which occasioned due to the faulty and substandard material
supplied by the claimant.
Â
C.      That the contents of sub para C of the claim-mental
pain & harassment are absolutely wrong, incorrect and reiterated, hence
specifically denied. It is denied that respondent is entitled to recover of Rs.x
Lacs for mental pain and harassment suffered by respondent in the hands of the
claimant.
Â
D.     That the contents of sub para D of the claim-loss
of goodwill and reputation are absolutely wrong, incorrect and reiterated,
hence specifically denied. It is denied that the respondent has suffered loss
of reputation and goodwill in the marker especially in the eyes of PSPCL and
the claimant is liable to compensate the respondent for the same to the tune of
Rs. xx Lacs.
Â
E.      That the contents of sub para E of the claim-litigation
cost are absolutely wrong, incorrect and reiterated, hence specifically denied.
It is denied that respondent is also entitled to recover and Rs.x Lacs as
litigation cost incurred by respondent solely due to the claimant.
Â
F.      That the contents of sub para F of the claim-interest
are absolutely wrong, incorrect and reiterated, hence specifically denied. It
is denied that the claimant is liable to pay interest @18% p.a. on the above
mentioned total claim amount of Rs. xxxxx/- till final adjudication of the
case.
Â
         It is submitted that the respondent is
not entitled to get any relief by way counter claim from the Hon’ble Arbitrator.
Â
Prayer clause along with its sub paras of the counter claim are
absolutely wrong and specifically denied. The respondent is not entitled to the
relief claimed for.
Â
         It is therefore most respectfully
prayed that the counter claims of the respondent may kindly be dismissed and relief
may kindly be granted in favour of the claimant as prayed in the statement of
the claimant, in the interest of justice, equity and circumstances of the case.
Â
Pass
such further order or orders as this Hon’ble Court may deem fit and proper of
the facts and circumstances of the case, in the interest of justice.
Â
It
is prayed accordingly.
Â
CLAIMANT
DELHI Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â THROUGH
DATEDÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â
(xxxxx)
ADVOCATE
xxxx
xxxx.
Â
BEFORE THE SOLE ARBITRATOR xxxxx ; xxxxx, xxxxx
Â
Arbitration Case No. ____ OF
2016.
In the matter of Arbitration between:
Â
M/S.
xxxxx
                                      CLAIMANT
VERSUS
xxxxx                                     RESPONDENT
Â
AFFIDAVIT
Affidavit of Mr.xxxxx , about ___ years, Director of M/s. xxxxx Having its Registered
Office at xxxxx, do hereby solemnly
affirm and declare as under:-
Â
1.      That
I am the Director of claimant company and I am conversant with the facts and
circumstances of the present case and as such am competent to swear this
affidavit.
Â
2.      That
the accompanying reply to the counter claims has been drafted under my
instructions, which has been read and understood by me and I say that the
contents of the same are true and correct.
Â
DEPONENT
VERIFICATION
:-
         Verified at Delhi on this ____, day of xxxxx that the contents of paras of the above affidavit are true and
correct to my knowledge. No part of it is false and nothing material has been
concealed therefrom.
Â
DEPONENT