BEFORE LD. SOLE ARBITRATOR;
DELHI
INTERNATIONAL ARBITRATION CENTER,
DELHI
HIGH COURT AT NEW DELHI.
ARBITRATION CASE NO. ____ of 2024.
IN THE MATTER OF:-
XXXXXXXXXXXXXXXXXXXXXXX :
CLAIMANT
VERSUS
XXXXXXXXXXXXXXXXXXXXXXX : RESPONDENTS
INDEX
|
S.NO. |
PARTICULARS |
PAGE |
|
1. |
STATEMENT OF CLAIM ON BEHALF OF THE CLAIMANT. ALONG
WITH AFFIDAVIT IN SUPPORT. |
|
|
2. |
ANNEXURE C-1 BOARD RESOLUTION DATED……. |
|
|
3. |
ANNEXURE
C-2 COPY OF WORK ORDER DATED xxxxx. |
|
|
4. |
ANNEXURE
C-3 COPY OF WORK ORDER DATED xxxxxx |
|
|
5. |
ANNEXURE C-4 COPY
OF TERMINATION LETTER DATED xxxxxx. |
|
|
6. |
ANNEXURE C-5 COPY
OF REPLY TO TERMINATION LETTER DATED xxxxxx. |
|
|
7. |
ANNEXURE C-6 COPY
OF LEGAL NOTICE SENT BY THE RESPONDENT DATED xxxxx. |
|
|
8. |
ANNEXURE C-7 COPY
OF NOTICE DATED xxxxxx INVOKING ARBITRATION. |
|
|
9. |
ANNEXURE C-8 COPY
OF REPLY OF RESPONDENT TO NOTICE OF ARBITRATION INVOCATION DATED xxxxxx. |
|
|
10. |
ANNEXURE C-9 COPY
OF REJOINDER TO THE REPLY NOTICE DATED xxxxxx. |
|
|
11. |
ANNEXURE C-10 COPY
OF LETTER DATED xxxxxx ISSUED BY PETITIONER FOR CLAIMS ALONG WITH ANNEXURE. |
|
|
12. |
ANNEXURE C-11 COPY
OF EMAILS EXCHANGED BETWEEN THE PARTIE. |
|
|
13. |
ANNEXURE C-12 COPY
OF ORDER DATED xxxxxxxxx REGARDING AIR QUALITY. |
|
|
14. |
ANNEXURE C-13 COPY
OF MINUTES OF MEETING DATED xxxxxxx, xxxxxxx, xxxxxxxxx AND xxxxx. |
|
|
15. |
ANNEXURE C-14 COPY
OF HINDERANCE REPORT ALONG WITH TRUE TYPED COPY. |
|
|
16. |
ANNEXURE C-15 COPY OF THE ARBITRATION PETITION BEARING NO………/2023
FILED BY THE CLAIMANT BEFORE THE HON’BLE HIGH COURT OF DELHI. |
|
|
17. |
ANNEXURE C-16 COPY OF THE ORDER DATED ……..2024 PASSED BY HON’BLE
HIGH COURT IN ARBITRATION PETITION BEARING NO……../2023. |
|
|
18. |
VAKALATNAMA |
|
DELHI CLAIMANT
THROUGH
DATED
x (Advocate)
Counsel
for Claimant
Off.: xxxxxxxxxxxx,
New Delhi-110019.
Mob. No.xxxxxxxxxxxxxxxx
Email: xxxxxxxxxxxxxxxxx
BEFORE LD. SOLE ARBITRATOR;
DELHI
INTERNATIONAL ARBITRATION CENTER,
DELHI
HIGH COURT AT NEW DELHI.
ARBITRATION CASE NO. ____ of 2024.
IN
THE MATTER OF:-
xxxxxxxxxxxxxxxxxx : CLAIMANT
VERSUS
1.xxxxxxxxxxxxxxxxxxx
2. xxxxxxxxxxxxxxx
3. xxxxxxxxxxx
All at xxxxxxxxxxx,
New Delhi-110045. : RESPONDENTS
STATEMENT
OF CLAIM ON BEHALF OF THE CLAIMANT.
MOST RESPECTFULLY
SHOWETH:-
1.
That
the petitioner is a Private Limited Company registered under the Companies Act,
1956 having its office at New Delhi, Delhi. The company, inter aha, is
engaged in the business of constriction. That owing to its distinguished
working style and transparency, the Petitioner has attained a commendable image
not only in the State of Delhi but in the entire country and is as such a
revered name in the industry.
2.
That as
per the information available at the web portal of MCA, xxxxxxxxx. i.e.
Respondent No. 1 is a Limited Liability Partnership (LLP) is based out of Delhi
and was officially incorporated on xxxxxx. That Mr. xxxxxxxxx, Respondent No. 2
and Mr. xxxxxxxxxxxxxxxx, Respondent No. 3 are the two Partners of Respondent
No. 1 who are responsible for the day-to-day operations of Respondent No. 1.
3.
That
after considerable negotiations between the Claimant and Respondents, the
Respondents were pleased to issue the Work Order dated xxxxxxx (hereinafter
referred to as "WO"), thereby, issuing the project at xxxx xxx,
New Delhi for the construction of a warehouse building with materials
(excluding concrete and steel) for die site situated at xxxxxx, xxxxx, Delhi in
favour of the Claimant as per the terms and conditions as mentioned and agreed
upon therein. It is pertinent to
mention that the respondents have since inception created hurdles in the
execution of the project which have further led to extreme mental pressure and
anxiety due to their misconduct, high-headedness and improper dealings in
relation to the WO.
4.
That
the Respondents are responsible for the day-to-day affairs of VSY Logistic Park
LLP and thereby it was their duty to adhere and comply with all the terms and
conditions of the WO in its letter and spirit as signed between the Claimant
and Respondents.
5.
That
the aforesaid final WO was sent and shared with the Claimant via email
on xxxxxxx whereas the hard copy of the same was collected from Respondents’ office
on xxxxxx. Thereafter, a hard copy of the said WO was signed by the Claimant on
the same day and sent back the Respondents on xxxxx.
6.
That
the several emails have been exchanged between the Claimant and Respondents,
wherein, the Respondents have admitted the fact that the project land was not
demarcated until mid xxxxx, thereby the actual physical possession of the
project land was only handed over to the Claimant on xxxxxx, i.e., the date on
which the WO was finally signed by the Claimant and handed over to the Respondents.
7.
Even
though the WO was prepared by mutual consent in the month of xxxxxxxx however,
the Respondents were unable to get the clearances and demarcation done on the
agreed-upon time period. Thus there was a delay at their end to hand over the
possession of the project site to the Claimant until end of xxxxxx
8.
As
per the terms and conditions of the WO, the agreed-upon time period within
which the construction was to be completed at the project land was seven months,
i.e., six months and two weeks is the initial stipulated time in the WO, and
thereafter grace period of another two weeks.
9.
Thus,
the stipulated time period of seven months was to mature on xxxxxxx, however,
to the Claimant's complete shock and dismay, an illegal termination letter was
served upon the Claimant on xxxxx. That the said termination letter dated xxxxxx
is completely flawed as the same has been issued without any reasonable grounds
for such termination. The Claimant has issued a detailed reply to their termination
letter on xxxxxx, to which the Respondents have neither paid any heed nor
bothered to respond till date.
10.
Moreover,
as the Respondents are also aware, there was a NGT Ban imposed for all
construction sites in Delhi which continued and extended for a period of 35
days because of which no construction work could be carried out. Therefore, in
the calculation of the time period within which the project site was to be
completed, this period of 35 days has to be added over and above the seven-month
period.
11.
Additionally,
there has been a delay and stoppage of work by 7-10 days which was due to the
NHAI work right outside the project site because of which the Claimant was
unable to bring his machines and raw materials in order to carry out
construction work. Several communications via emails and WhatsApp Chats have
been exchanged between the parties wherein the Respondents have accepted the
fact that the entry to the project site was blocked and accordingly the Respondents
had sought time to resolve the said issue with NHAI. As per the terms and
conditions contained in the WO, the access to the project site was the
responsibility of the Respondents and any hindrance in execution of scope as
per the WO has to be accounted for and the Claimant deserves the extension of
the very same days.
12.
That
the Respondents have also been made aware of the fact that there was delay of
10-12 days due to shortage of concrete. The shortage of concrete was due to the
Respondents negligence as the said duty and responsibility as per the WO was
casted upon Respondents, in order to provide concrete to the Claimant at the
project site. The said
fact is recorded and evident from the various emails/ WhatsApp chats wherein
the Respondents have admitted shortage and delay in providing concrete to the Claimant.
13.
Further,
as per the terms and conditions contained in the WO, it was the Respondents duty
to provide drawings of PT Beam and boundary walls which were to be installed
and constructed at the project site. There has been a delay of more than one
month as the Respondents failed to provide the same as per the agreed-upon time
lines. The said fact is evident and established from the most recent drawing
which was sent by the Respondents only on xxxxx, i.e. 17 days prior to issuing
the termination letter dated xxxxxxxxxx, showcasing and portraying the
malafide, irresponsible intention and behaviour of the Respondents, to cause
grave loss to the Claimant.
14.
That
if the aforesaid delays, i.e., the NGT Ban or inordinate delay at their end due
to missing drawings, shortage of concrete and restricted entry to the project
site are to be calculated and accounted for then the Claimant is legally bound
and entitled to get additional 90-100 days, for the completion of the work at
the project site, which automatically takes the project completion date to xxxxxxx.
The aforesaid delays and extension of time period have been recorded in various
communications between the parties through emails and WhatsApp chats, wherein
the Respondents have also admitted their fault and time and again the Respondents
have been seeking time to rectify these issues as raised by the Claimant.
15.
That
the Respondents negligent and irresponsible behavior have caused grave
financial loss and mental harassment to the Claimant. Even then due to the long
held mutual admiration, the Claimant has tried to resolve these issues amicably
but the Respondents have failed to show any keen interest in settling the
outstanding claims towards the Claimant.
16.
That
even after the Respondents have illegally terminated the WO which has caused
grave financial loss to the Claimant, the Claimant's endeavour has been to
resolve the dispute amicably and accordingly shared the detailed claim with the
Respondents through email and also handed over a hard copy of the claim/ dues
to their staff along with all the supporting data and details.
17.
However,
to the Claimant's utmost surprise, the Respondents after a period of one month
have raised a baseless counter-claim which is rather contrary to the WO signed
between the parties. This illegal and unsubstantiated counter-claim raised by
the Respondents proves their malafide intentions to not settle the
legitimate claims raised by the Claimant on amicable terms and further shows their
ill intentions to cheat the Claimant and cause further financial hardships/
losses to the Claimant.
18.
That
the Claimant has attempted to engage with the Respondents on disagreements and
disputes which they have created, however, any and all efforts of the Claimant have
failed as the Respondents have refused to cooperate so as to settle the
legitimate claims and disputes as raised by the Claimant.
19.
That
the Claimant is left with no other option but to invoke the arbitration clause
as stipulated in the WO so as to recover the dues which the Respondents have
very conveniently withheld and refused to pay to the Claimant which is causing
grave financial loss to the Claimant.
20.
That
by way of the legal notice dated xxxxxx the Claimant in terms of the WO, due to
gross violation and breach of terms of the WO invoked the Arbitration Clause.
The relevant extract of the Arbitration Clause B of the Work Order applicable
to the present case is reproduced herein below for ready reference;-
‘’If
the dispute cannot be resolved pursuant to Clause A above within 10 calendar
days of the commencement of negotiations , the dispute shall be referred to and
finally resolved by arbitration administered under the Arbitration and
Conciliation Act,1996, as amended (the Arbitration Act), by a sole, Arbitrator.
M/s xxxxxxxx LLP shall suggest 3 independent and distinguished persons out of
which the agency shall choose one person to act as the sole arbitrator. The
seat of the Arbitration shall be in New Delhi, India. The proceedings of the
Arbitration shall be in English Language. The Arbitrator(s) shall also decide
on the costs of the arbitration proceedings. The arbitration award shall be
final and binding on the parties subject to applicable law in force and the
award shall be enforceable in any court of competent jurisdiction in India.
During the pendency of the arbitration
proceedings , the parties shall continue to perform such of their obligations
that are not the subject matter of the Dispute under this Agreement.’’
21.
The
process provided under Clause A of the Work order is now exhausted on account
of respondents lack of cooperation and the said clause is being invoked by the Claimant
by way of the notice dated xxxxxxx and made request to the respondents to suggest
and share 03 (three) independent names of the arbitrators, within a period of
15 days from receipt of said notice for adjudication of the dispute in terms of
the WO.
22.
That
it is pertinent to mention that on xxxxxxx the Claimant served the notice of
invocation of the arbitral clause under the WO dated xxxxxx to the Respondents.
It is trite to mention that the respondents replied vided reply dated xxxxxx
suggesting three names of Arbitrators, however vide response to the said reply,
the Claimant responded in rejoinder vide notice dated xxxxx not agreeing to the
said names suggested by the respondents. Thus by such conduct of the
Respondents, it is evident that the Respondents are not only in the breach of
its contractual mandate but also disrespects the rule of law and the only
objective of the respondents is to delay the present dispute between the Claimant
and Respondents.
23.
That the Claimant has been compelled to
invoke the arbitration clause, which had been incorporated to combat such
disputes arising between the parties for the resolving of disputes or settlements
of such matters between the parties relating to the agreement as narrated above.
24.
That in light of the aforesaid, the Claimant
herein was constrained to approach the
Hon’ble Delhi High Court and file Arbitration Petition bearing no………. of 2023 under
Section 11(6) of the Arbitration and Conciliation Act, 1996 for the appointment
of sole arbitrator under the aegis of Delhi International Arbitration Center.
Accordingly the Hon’ble High Court vide order dated ……2023 was pleased to refer
the disputes under the ageism of DIAC and constituted the present arbitration
tribunal.
25.
The
Claimant craves leave of this Hon’ble Tribunal to rely upon various documents
in support of the Statement of Claim, which are being filed herewith. By way of
abundant caution and in the interest of justice, the Claimant craves leave of
this Hon’ble Tribunal to place any other/further documents, which the Claimant
may discover subsequently and finds the same to be of relevance and worthy of
assisting this Hon’ble Tribunal in arriving at a just decision.
In light of the
above, it is humbly prayed as follows:
PRAYER:-
In
view of the above, the Claimant humbly prays that this Hon’ble Tribunal may be
pleased to Award the following in favor of the Claimants:-
i)
Pass an award in favour of the Claimant
and direct the respondents to make the payment of Rs. xxxxx/- (xxxxxx only)
with interest 18% from its due date till date of realization of the payment.;
ii)
Pass an award in favour of the Claimant
and direct the Respondents to pay other charges incurred by the Claimant because
of the mis-representations and false assurances made by the respondents.
iii)
Direct the Respondents to pay all legal
costs incurred by the Claimant in pursuing/defending legal proceedings before
the Courts in Delhi and the present arbitration proceedings along with interest
at the rate of 18% p.a.;
iv)
Direct the Respondent to pay pendent lite
interest at 18% to the Claimant on all sums found due and payable from May, 2022
till the date of conclusion of the present Arbitration proceedings.
v)
Award any other and further reliefs as
this Hon’ble Tribunal may deem just and proper in the facts and circumstances
of the case.
vi)
To pass any further order(s) or
direction(s) as this Hon’ble tribunal may deem fit, proper and necessary in the
facts and circumstances of the present case and in the interest of justice.
DELHI CLAIMANT
THROUGH
DATED
(Advocate)
Counsel
for Claimant
BEFORE LD. SOLE ARBITRATOR;
DELHI
INTERNATIONAL ARBITRATION CENTER,
DELHI
HIGH COURT AT NEW DELHI.
ARBITRATION CASE NO. ____ of 2024.
IN THE MATTER OF:-
XXXXXXXXXXXXXXXXXXXXXXX : CLAIMANT
VERSUS
XXXXXXXXXXXXXXXXXXXXXXX : RESPONDENTS
AFFIDAVIT
2. That
the submissions as to facts made in the statement of Claim under Rule-15 of the
DIAC (arbitration proceedings) Rules, 2018 has been drafted by my counsel and
the averments contained therein are true and correct to my knowledge, while the
legal submissions made therein are based on legal advice received and believed
to be true.
3. That the annexures annexed to the Statement
of Claim are true to their respective originals.
DEPONENT
VERIFICATION :-
Verified
at Delhi on this _____, day of February, 2024 that the contents of this
affidavit are true and correct to the best of my knowledge and belief and
nothing material has been concealed therefrom.
DEPONENT